Welcome to latest edition of the I-405/SR 167 Program newsletter, where we provide regular updates about impactful construction along the corridor.
People should prepare for closures on the north end of the I-405 corridor in Kirkland and Bothell this week. In this issue, you’ll find the latest closure information, a summary of work completed, and a preview of what’s coming next so you can “know before you go.”
We’re launching a new WSDOT Engage page to make it easier for you to stay informed. The page brings together construction and closure information, and ways to share your feedback all in one place. You will also find a list of upcoming impactful closures to help you plan ahead. Visit the new page to learn more: I-405/SR 167 Construction | WSDOT Engage.
This weekend, the I-405/Northeast 85th Street interchange in Kirkland will close for crews to complete electrical installation and prepare for paving, as part of the I-405/Northeast 85th Street Interchange and Inline BRT Station Project.
Crews will also conduct lane reductions and rolling slowdowns on southbound I-405 on Friday night to shift traffic and create a work zone, as part of the I-405/Brickyard to SR 527 Improvement Project.
Travelers are advised of additional closures on I-90 and SR 520 happening this week and a full closure of the I-5 express lanes.
Other WSDOT work to be aware of: Overnight lane and ramp closures on I-405 for maintenance Sept. 8-10
Separate from our program’s work, overnight lane and ramp closures along multiple state highways in King County will take place Sept. 8-10, for crack sealing and pavement repair. The list of closures can be found in this travel advisory and the WSDOT real-time travel map.
This is part of a regional pavement repair project addressing more than 70 locations in King, Snohomish, Skagit and Whatcom counties. These roadway improvements extend the life of the roadway and improve the driving surface.
I-405/Northeast 85th Street interchange closure in Kirkland, Sept. 11-14
The northbound and southbound I-405 on- and off-ramps (Exit 18) in Kirkland will close starting as early as 10 p.m. Friday, Sept. 11 until 5 a.m. Monday, Sept. 14.
Northeast 85th Street will also close between Sixth Street to 120th Avenue Northeast. Detours will be in place.
 Detour route for Northeast 85th Street/Interstate 405 intersection closure (Sixth St to 120th Ave NE).
Overnight lane reductions rolling slowdowns on southbound I-405 in Bothell, Sept. 11-12
Up to three lanes of southbound I-405 will close between SR 522 and Northeast 160th Street from 8 p.m. Friday, Sept. 11 to 5 a.m. Saturday, Sept. 12. The eastbound and westbound SR 522 ramps to southbound I-405 will also close during this time.
Crews will conduct rolling slowdowns during the lane reductions where they will stop traffic for up to 15 minutes at a time between 11:59 p.m. and 4 a.m.
Upcoming work
Sept. 11-14
- I-405/Northeast 85th Street interchange closure in Kirkland
- Overnight lane reductions and rolling slowdowns on southbound I-405 in Bothell
Sept. 16-17
- Overnight closure of I-405/Northeast 85th Street interchange in Kirkland
Sept. 18-21
- Northbound I-405 closure from Renton to Bellevue
- I-405/Northeast 85th Street interchange closure in Kirkland
This schedule is subject to change due to the nature of construction. Weather, traffic conditions, equipment availability, and other factors can affect scheduled work.
In addition to these impactful closures, expect nighttime lane and ramp closures and ongoing construction along the I-405 corridor. Check the real-time travel map for alerts.
Recent accomplishments
All-hands-on-deck on northbound I-405 in Bothell
Crews started pouring fresh concrete for the new northbound I-405 bridge deck in Bothell, as part of the I-405/Brickyard to SR 527 Improvement Project. Constructing a new northbound I-405 bridge deck at the I-405/SR 522 interchange will allow crews to add an express toll lane (ETL) in each direction and direct access ramps from SR 522 to the ETLs.
 Crews poured the deck for a new section of northbound I-405 in Bothell the week of Aug. 31, 2026.
Keep in touch
We want to hear from you. Please reach out if you have questions or comments.
Email: I405SR167Program@wsdot.wa.gov
24-hour hotlines for construction:
- I-405/Brickyard to SR 527 Improvement Project | 425-354-3232
- I-405/Northeast 85th Street Interchange and Inline BRT Station Project | 425-224-2423
- I-405/Renton to Bellevue Widening and Express Toll Lanes Project | 425-818-0161
Resources
WSDOT Engage | WSDOT travel map | WSDOT mobile app | Flickr
Social media
X | Threads | Facebook | Instagram | Reddit
Webpages
|