I-94 Project Update
Michigan DOT sent this bulletin at 07/27/2020 03:27 PM EDT
Having trouble viewing this email? View it as a Web page. |
CONTACT: MDOT Jackson Transportation Service Center
517-780-7540
mdot-jacksontsc@michigan.gov
I-94 Project Update
July 27, 2020 – In the upcoming week, crews will continue reconstructing the median of I-94 by pouring a concrete barrier wall on westbound and eastbound I-94. Additionally, from Elm Avenue to Sargent Road, the contractor is working on grading and placing a concrete base course in the median.
Maintenance of traffic for this upcoming week will include, traffic being maintained on I-94 with a “split-merge” configuration and reduced speed zones along I-94 between Sargent Road and Elm Avenue. Traffic will be maintained between Elm Avenue and Lansing Avenue with shoulder closures and reduced speed zones.
An I-94 Construction Video has been uploaded to YouTube and provides further information about the ongoing project.
For more information about the I-94 project, go to www.michigan.gov/i94jackson. The project website contains various visual aids including a link to our Construction Photos, a link to the most recent I-94 public meeting presentation, and additional links to project-related questions and answers.
###
Protect workers. Protect drivers. Safe work zones for all. www.Michigan.gov/WorkZoneSafety