Construction Alert
July 2, 2024
|
|
NOTE: You are currently signed up to receive Construction Alerts for the Foothill Gold Line light rail project. If you would like to unsubscribe from Construction Alerts but still receive the monthly project E-News Updates, click here.
|
|
CONSTRUCTION ACTIVITY
As part of the 9.1-mile Foothill Gold Line light rail project, active train testing will begin to take place daily and nightly throughout the project (from between Barranca Ave in the City of Glendora to past Garey Ave in the City of Pomona) starting Monday, July 8th and continuing through the end of 2024. Testing will occur Monday thru Friday, specifically during shifts as shown below. Regularly scheduled construction activities will also continue. Train testing, using an active train, will occur with the help of local police departments and the Los Angeles County Sheriff directing traffic at the grade crossings. To limit noise, the grade crossing bells will be disconnected as much as possible during this testing period and the train operators will use their optional “quiet-zone” horns as much as possible. Please follow all safety instructions and be aware of active trains and dropping crossing gates at railroad crossings project wide.
WHEN
Beginning Monday, July 8th and continuing daily/nightly thru December 31st, 2024. Testing will occur Monday – Friday as follows:
-
July 8th – 12th: Daily testing; 7:00 AM – 4:00 PM (longer hours may be needed occasionally)
-
July 15th – December 31st: Nightly testing; 6:00 PM – 4:30 AM (longer hours may be needed occasionally)
NOTE: Additional daytime/nighttime testing may occur, including on Saturdays and Sundays if needed.
TRAFFIC ADVISORIES
- Crossing gate arms will drop throughout the work shift when testing is taking place.
- Vehicular and pedestrian traffic will be stopped when gates are down; and resume as normal once gate arms are raised.
NOTE TO RESIDENTS
- Never walk on the train tracks.
- Never go around the lowered gates and follow all safety instructions.
- Obey all warning signs and watch for trains from both directions.
MAP
Click here to view the construction notice in PDF
To see other current and upcoming construction activities that may impact you, visit the interactive construction map page at www.foothillgoldline.org.
|
|
Contact Information for General or Construction-Related Questions
Have questions about the Foothill Gold Line project or construction? Here is how you can get your questions answered:
By Phone or Email:
The Kiewit-Parsons JV team has a construction hotline and email address for construction-related questions; while general project questions should continue to be sent to the Construction Authority:
Project Construction Questions: Hotline: (626) 513-5788 Email: CommunityRelations@Kiewit-Parsons.com
General Project Questions: Call: (626) 471-9050 Email: PublicAffairs@Foothillgoldline.org
In Person:
Construction Authority Headquarters 406 E. Huntington Dr., Suite 202 Monrovia, CA 91016 Office Hours: Mon – Thurs, 9 AM – 4 PM
Construction Public Information Office 2100 E. Route 66, Suite 200 Glendora, CA 91740 Office Hours: Mon – Fri, 8 AM – 4 PM
|
|
|
|