7/23/2012
SourceGas Distribution LLC
Order to Show Cause and Notice and Order Initiating Investigation
IN THE MATTER OF THE COMMISSION INVESTIGATION TO
DETERMINE WHETHER SOURCE GAS DISTRIBUTION, LLC, IS
EXCEEDING ITS AUTHORIZED RATE OF RETURN, SUCH
THAT ITS RATES ARE NOT JUST AND REASONABLE AND
ORDER TO SHOW CAUSE WHY ITS RETAIL RATES SHOULD
NOT BE REDUCED
http://psc.state.wy.us/htdocs/orders/30022-192-20881.htm
7/23/2012
Black Hills Power, Inc.
Order Letter
IN THE MATTER OF THE JOINT APPLICATION OF CHEYENNE
LIGHT, FUEL AND POWER COMPANY AND BLACK HILLS
POWER INC., FOR A CERTIFICATE OF PUBLIC CONVENIENCE
AND NECESSITY FOR CONSTRUCTION, OPERATION AND
MAINTENANCE OF A GAS-FIRED ELECTRIC GENERATING
POWER PLANT AND RELATED FACILITIES
http://psc.state.wy.us/htdocs/orders/20003-113-20879.htm
7/23/2012
MGTC, Inc.
Order Letter
IN THE MATTER OF THE AMENDED APPLICATION OF MGTC,
INC. FOR A GENERAL RATE INCREASE IN THE AMOUNT OF
$486,936 PER YEAR AND FOR APPROVAL OF TARIFF