Alleyway work: Nov. 19–Dec. 2
- A work crew will perform alley improvements between 1st Street NW and 2nd Street NW, as part of the Auburn Garage Project. This work will include asphalt grinding, pavement repairs, and asphalt placement. These improvements will affect vehicle access through the alley.
When
-
Work will begin at 7 a.m. on Thursday, Nov. 19, and end by 8 p.m. on Wednesday, Dec. 2.
-
The roadway surface will be gravel during construction.
-
Vehicle access will be closed on Nov. 19 for grading and again on Dec. 2 for paving.
-
Parking in the alley will be unavailable on Nov. 19, 7 a.m.–7 p.m. Expect delays entering and exiting the alley from Nov. 23–25. Parking will be unavailable again on Dec. 2, 7 a.m.–8 p.m.
Where
- The work will take place in the alley between 1st Street NW and 2nd Street NW in Auburn.
More
-
ADA ramp access will remain available during asphalt grinding and repair work.
-
The contractor will conduct grinding on Nov. 19, grading from Nov. 23–25, and paving on Dec. 2.
-
During asphalt placement on Dec. 2, the ramp will be temporarily inaccessible all day as the asphalt cools and cures. This work is weather-dependent, so it may shift.
-
Residents are encouraged to make alternate parking arrangements during the closure.
-
Please ensure your cars are moved before 7 a.m. on Nov. 19 and Dec. 2.
-
Two on-street parking spaces in front of 129 A St NW, Auburn, WA 98001 will remain available for resident use during the work.
Contact us
Outreach Specialist: auburngarage@soundtransit.org or (253) 303-3766
After-hours construction hotline: 888-298-2395
|
|