Beginning as early as Monday, July 10, crews will be closing Cleveland Street in Downtown Redmond between 164th Avenue Northeast and 166th Avenue Northeast. Cleveland Street will be closed to people driving, walking, or rolling so work may be performed on the roadway and sidewalk.
Pedestrian access to local businesses will be maintained at all times.
What
- Ongoing closures of Cleveland Street in Downtown Redmond
Where
- Cleveland Street between 164th Ave NE and 166th Ave NE
When
- Closures will begin on Monday, July 10, and will be in place intermittently through the second week of August.
- Cleveland Street will be reopened for Derby Days on July 15 and July 16.
- Cleveland Street will also be reopened between July 21 and July 31.
More
- A noise variance has been obtained to complete this work
- Pedestrian access to local businesses will be maintained at all times
- Due to inclement weather or unforeseen issues, dates and times are subject to change.