Construction alert: Lynnwood Link Extension

Having trouble viewing this email? View it as a Web page.

Construction alert

Closures on 48th Ave. W and 200th St. SW

As early as Tuesday, June 13, Sound Transit’s contractor will continue work along 200th Street SW and 48th Avenue W. The right lanes on both 200th St. and 48th Ave. will be closed. A full closure of 200th St. SW will begin on Friday, June 16. Detours will be provided (see map).

What

  • Lane closures on 200th St. SW and 48th Ave. W, as well as a full daytime closure of 200th St. SW for roadway improvements.

When

  • 200th St. SW and 48th Ave. W lane closures will take place Tuesday, June 13 – Friday, June 16, from 7:30 a.m. to 4 p.m.
  • 200th St. SW full closure will take place Friday, June 16, from 8:30 a.m. to 4 p.m.

Where

  • 200th St. SW, between 48th Ave. W and Cedar Valley Road

More

  • Detours will be provided (see map).
48th st closure

Starting 6/13: Right lane closure on eastbound 200th St. SW and southbound 48th Ave. W.


200th St

Starting 6/16: Closure of 200th St. SW between 48th Ave. W and Cedar Valley Road. Right lane closure of 48th Ave. W. Detours shown.

More updates


Your safety is our priority

Learn how to stay safe around our construction sites.

Stay safe

24-hour construction hotline: 888-298-2395

After-hours construction hotline: 888-298-2395

More project info: soundtransit.org/lynnwoodlink
Get in touch: Outreach Specialist Dani Schmitt – dani.schmitt@soundtransit.org