As early as Monday, Feb. 6, contractors will be performing night work from along the Sound Transit guideway, at the Shoreline Fire Department Station 65 driveway. This is a part of the Light Rail Lynnwood Link Extension project. The work will consist of a concrete saw cutting and the use of light plants. Given weather conditions, work will proceed as weather permits.
What to know:
- Residents should expect noise from a concrete saw, light plants and vehicles.
- The work will take five nights, with the dates noted below. There are multiple contingency nights scheduled in case the work is delayed.
- If the work is delayed or take longer than expected, more days will be added and a new flyer will be provided to residents.
When:
- Monday, Feb. 6, through Friday, Feb. 10, from 8 p.m. to 4 a.m. the following mornings.
Where:
- Work zone is located on NE 155th St. along the Sound Transit guideway at the Shoreline Fire Department Station 65 driveway.
- See map for work area.
 Contact us
Community Engagement: c-jaybee.ragudo@soundtransit.org or 206-701-1469 After-hours construction hotline: 888-298-2395
Learn how to stay safe around our construction sites.
|