Construction alert: Hilltop Tacoma Link Extension

Having trouble viewing this email? View it as a Web page.

Project update email banner for Hilltop Tacoma Link Extension

Construction alert

Image of Stadium District Art Install, Hilltop Tacoma Link Extension Construction Alert

Weekly Construction Update: Traffic control impacts and night work along the Hilltop Tacoma Link project area for the week of July 28th.

Construction activities are occurring throughout the Hilltop Link Extension project area that include crews continuing to finish the roadway restoration, working on station finishes, adjusting utilities, paint striping on the street, systems testing, installing crosswalks in various locations along the Hilltop Tacoma Link project area.  Work is scheduled to start on Monday, August 1st at 6am on the 9th and Commerce cutover, which will work on connecting the existing Tacoma Link line to the Hilltop Tacoma Link Extension.  Please allow for extra travel time to get to your destination and follow detour signage.  For details of the traffic control impacts please scroll down to the “Where” section.

Access is open to hospitals, medical centers and the emergency department during construction.

Please support your local businesses during construction and stay Loyal to the Local!

What

Construction and traffic restrictions along Stadium Way, N. 1st Street, N. 2nd St., Division Avenue, Martin Luther King Jr. Way and the Dome District

When

  • July 28th Update (Inclement weather or unforeseen issues will push dates and times). Work will occur during the day and nighttime hours. 

Where

Various locations along the project area:

  • Daytime and nighttime track testing, electrical testing and overhead wiring work for the future light rail system will be occurring in various locations along the alignment during the week (Commerce St., Stadium Way, N. 1st, Division Ave., and MLK Jr. Way). During this construction activity the contractor has obtained a nighttime noise variance and will need to temporarily remove parking and shift traffic to maintain a safe working area.
  • Station art installations will occur throughout the project area and will require traffic control during the work to safety raise the art onto the station.

Dome District:

  • Westbound E. 25th Street between G and K streets closure due to restoration.

Commerce/Stadium Way:

  • Southbound closure of Stadium Way/N. E Street/N. 1st between N. Broadway St. and 705. Will reopen next week (8/1) during the daytime hours but will be closed during the nighttime hours for the next two weeks.  Nighttime work on Stadium Way to perform electrical and track clearance testing.
  • 9th Street and Commerce St. intersection closure with local access only on Commerce Street between S. 7th and S. 11th streets starts on August 1st at 6am and is scheduled to reopen September 16th. The contractor is planning on connecting the existing T Line (Tacoma Link Line) to the Hilltop Tacoma Link Extension project. This will require a long-term intersection closure of 9th and Commerce and a nighttime noise variance with 24-7 work hours. Traffic detours will be in place with crosswalk and pedestrian access closures at the intersection of 9th and Commerce St. The construction work includes utility relocation, systems installations, installing track slab, roadway restoration, demolition of the current Theater District Station and pedestrian ramps. During this work the Tacoma Link Line will be closed and there will be a bus shuttle providing transit service in the corridor, similar to what occurred for the T-line closure last summer on Pacific Ave. (more details of the closure here).

Stadium District (N. E St., N 1st St., Division Ave.):

  • Eastbound North 1st Street eastbound closure between. Yakima and N. Tacoma avenues is scheduled to be closed and reopened by August 6th. Future nighttime closures and work of N. 1st Street will be needed in the future in both directions.
  • Tacoma Ave. and N. 1st Street work which includes the restoration of all 4 corners work starts on August 1st. When this work starts the crosswalks will need to be closed to restore the sidewalk, ramps and utilities. Vehicle and sidewalk access will be maintained.  Parking will need to be removed near work areas.  Some of the work will require lane closures to N. Tacoma Ave. and N 1st St.
  • Southbound I Street closure at Division Ave. This work will be completed during the weekdays and weekends. This work should be completed by mid/late August.
  • Future street closures:
    • Division Ave. and MLK Jr. Way full intersection closure is scheduled to start on August 19th to complete the sewer installation.
    • N 2nd Street from N Yakima Ave. and I Street full street closure for roadway has been temporarily opened but is scheduled to return August 19th.
    • Northbound N. Tacoma Ave NB Closure at N. 1st Street will occur at a future date.
    • South and North J Street full closure at Division Avenue will occur at a future date.

Hilltop/MLK Jr. Way:

  • Northbound MLK Jr. Way road closure between S. 6th Avenue and S. 9th S. 6th Avenue between MLK Jr. Way and S. J Street is closed to thru traffic.  Local access to alley is maintained.  This is scheduled to reopen by next week by August 1st.
  • 8th Street closure from MLK Jr. Way to S. L St. This is scheduled to open sometime next week.
  • Earnest S Brazil Street closure between MLK Jr. Way and S. J Street. Local access to the alleys are maintained.
  • Northbound MLK Jr. Way road closure between S. 17th and S. 19th streets
  • Future street closures:
    • S. 11 Street between MLK Jr. Way and S. L Street closure is scheduled to close for restoration and crosswalk work starting as early as August 15th (work is dependent on the above work schedules).
    • S. 15th Street between MLK Jr. Way and S. J Street closure is scheduled to start mid/late August (work is dependent on the above work schedules).
    • S. 9th Street between MLK Jr. Way and S. J Street closure will occur at a future date

 More

  • Cross the street at only designated crosswalks. For wheelchairs, walkers, strollers, and bicyclists, cross tracks at a right angle. Obey all traffic signs and signals.
  • Driveway and pedestrian access are maintained, although some sidewalks and crosswalks will be temporarily closed. Pedestrian detours will be in place.
  • Buses will follow detour routes. Visit PierceTransit.org for information.
  • Construction noise related to removing pavement and operating equipment.
  • Large construction equipment or materials may be in the right-of-way.
  • Work will occur during the daytime and nighttime hours. Saturday work can start as early as 7am. 
  • Businesses are open during construction. Supports your local business and stay Loyal to the Local!
  • Plan ahead and allow extra time to reach your destination.
  • Due to inclement weather or unforeseen issues, dates and times are subject to change.

Contact us

Community Engagement: htlink@soundtransit.org or 206-398-5300
After-hours construction hotline: 888-298-2395

More updates


Your safety is our priority

Learn how to stay safe around our construction sites.

Stay safe

24-hour construction hotline: 888-298-2395

More project info: soundtransit.org/htlink
Get in touch: htlink@soundtransit.org or 206-398-5300