Starting Monday, November 22nd, Sound Transit’s contractors will begin making traffic changes at the NE 185th and 5th Ave NE undercrossing near Shoreline Stadium.
What
- The one-way signalized traffic light will be removed as the road conditions will be shifted to two-way traffic.
- Bicyclist lane will be closed and reduced to same lane as vehicles.
- Sidewalk will be closed.
- Residents can expect construction noise from equipment being operated.
- Sound Transit’s contractor will continue work on the north side of the NE 185th undercrossing.
When
- Temporary striping work with begin Monday Nov. 22-23 from 10:00 p.m. to 6:00 a.m.
- NE 185th and 5th traffic modifications duration will last until Summer of 2022.
Where
- NE 185th and 5th Avenue undercrossing.
- See map for more details.
Contact us
Community Engagement: my.nguyen@soundtransit.org or 206-370-5690 After-hours construction hotline: 888-298-2395