Project update: Northgate Link Extension

Having trouble viewing this email? View it as a Web page.

Project update:

Northgate Link Extension

Northgate Link Construction Update

The Northgate extension is humming along, and construction is on schedule at about 68% completion. Most of the major underground structural work on the stations is complete, and the trackway is nearly ready for electrical and communication systems installation.


University District

Big changes are happening to the University District station! As you may have noticed, crews have removed the temporary street at NE 43rd this summer. Designed by LMN Architects, Sound Transit’s contractor, Hoffman Construction Company removed the temporary street to prepare for the placement of the roof over the south end of the underground station. The contractor also started building out the escalators, elevators, electrical and mechanical systems in the stations interior. Soon, work will begin on the north and south head houses, which encase the mechanics of the escalators and elevators, as well as provide ventilation.  

Sound Transit is also sponsoring “Up Your Ave” on Friday, September 28 from 3 p.m. – 6:30 p.m. The University of Washington and U District Partnership is hosting this event to welcome incoming and returning UW students to the neighborhood by encouraging them to explore the various businesses on “The Ave.” Sound Transit will have a booth to provide information and answer questions about the Northgate Link Extension.

Platform level of the U District Station, prior to roof installation
Platform level of the U District Station, prior to roof installation.

Roosevelt 

More good news! The underground Roosevelt Station, designed by Hewitt Architects, has made its way above ground. With 4,661 cubic yards of concrete placed, the roof covering the station is complete. The Hoffman Construction crew are now working on constructing the stations north and south head houses. Neighbors and passersby can see the steel structure peeking over the green sound walls. The Roosevelt station recently marked another milestone – all construction activities at Roosevelt station authorized by the Major Public Project Construction Noise Variance permit (MPPCNV) is finished. This permit was in place to complete the 24-hour a day tunneling work, safely and on schedule. Any remaining station work that must be done outside of normal construction hours requires a temporary noise variance permit. Sound Transit will notify neighbors of any work occurring outside normal construction hours. 

The MPPCNV will continue to support ongoing night work at the University District station related to the construction of floating slab in the vicinity of the University of Washington campus.

What’s next? The tower crane will be dismantled this fall, and some of the green sound walls will be removed in stages and replaced with temporary fencing. Stay tuned for details.

Image of Roosevelt Station’s north head house which will house the escalators and elevators and provide ventilation.
Roosevelt Station’s north head house which will house the escalators and elevators and provide ventilation.

Northgate Station guideway 

If you’ve been around the Northgate area, you probably noticed the construction of the Northgate Link Light Rail Station is progressing quickly. Whether driving through Northgate on I-5, taking a trip to Northgate Mall or heading to your home or workplace in the neighborhood, it’s hard to miss the continuous guideway leading to the future Northgate Station. It is, after all, approximately 2,500 feet long. That’s nearly half a mile!

The guideway was constructed in phases, connecting 57 precast concrete girders, which are beams placed on columns that support the guideway structure. It weighs in at a whopping 11.5 million lbs. Sound Transit’s contractor, Absher Construction Company, erected the first precast girder in June 2017, and in May 2018 erected the final girder to create a continuous elevated guideway from the Maple Leaf Portal to the future elevated Northgate Station. Rail installation will begin in 2019.

See the transformation with the two drone videos highlighting the Northgate station: the first in the early phases of construction in January 2017 and the second in August 2018 showing substantial completion of the elevated guideway.

Click here to see early guideway construction – January 2017

Click here to see substantial guideway completion – August 2018

Aerial view of the Northgate Station elevated guideway looking southwest.
Aerial view of the Northgate Station elevated guideway looking southwest.

For more information