Sections of I-90 Trail on North Mercer Island to close near Shorewood Drive, and between Island Crest Way and 84th Avenue Southeast for final paving as early as May 5 for final paving |
|
Expect pedestrian and bike detours
|
|
Milling I-90 Trail
s early as May 5, crews will mill sections of the I-90 trail by Shorewood Drive, and in a second section of the trail between Island Crest Way and 84th Avenue Southeast in preparation for paving. This work is expected to take up to two days to complete.
 Map of work areas with pedestrian and bike detours. Sections of the I-90 Trail will be closed for trail paving near Shorewood Drive, and between Island Crest Way and 84th Avenue Southeast. Please follow marked detours and travel slowly around the work area
Paving the Trail
Once milling is complete, crews will pave the trail. This work is expected to take up to two days to complete.
Milling and paving is weather dependent and may take longer or be rescheduled.
Trail detour
During this work, the pedestrian detour will be routed along a temporary gravel path while cyclists will be detoured to merge with traffic along N. Mercer Way and follow I-90 trail where routed (see map). Please follow all detour signs and travel slowly around the work area. Certain portions of the trail may reopen dependent on areas that need repair.
Please follow marked detours and signs. Drivers should use extreme caution while moving through this area.
|
|
What to expect:
- Approved work hours are 7 am to 7 pm Monday to Saturday.
- All work will be performed in the public right-of-way.
- Noise, dust, and vibrations typical of an active construction project.
-
Grinding will create additional noise and vibrations.
- Emergency vehicle access will be maintained.
- Construction schedules can change based on factors such as site conditions, weather, and material availability. Please visit the project website for updates.
|
|