Restoration work at Fruitland Landing begins as early as December 1 |
|
Expect alternating single lane traffic with flaggers |
|
|
Crews have been testing and starting the commissioning process at Lift Station 11 in Fruitland Landing over the past few weeks. Restoration work on 97th Avenue Southeast and areas in Fruitland Landing will begin as early as December 1.
Bypass pipe removal
Starting December 1, crews will deactivate, flush, and remove the temporary bypass piping and access ramps along driveways on the north end of 97th Ave SE. This work is expected to take up to 3 days to complete. Residents may experience brief delays of up to 10 minutes when accessing their driveways during removal.
Backfill and temporary paving
As early as December 3, crews will backfill the intersection of 97th Ave SE and Southeast 34th Street.
|
|
During work hours, there will be alternating single lane traffic directed by flaggers around the work area. Drivers may experience short delays of a few minutes. Driveway access will be maintained at all times, and the intersection will reopen to two-way traffic outside of work hours. This work is expected to take one day to complete.
|
Crews will remove the bypass pipe and access ramps along 97th Ave SE. Then, they will backfill and pave the intersection at 97th Ave SE and SE 34th St. During work hours, flaggers will direct single lane traffic around the site.
|
As early as December 4, once backfilling is complete, crews will begin temporary paving of the intersection. Paving is expected to take up to two days. If you plan to leave your home during permitted work hours (7 a.m. to 7 p.m.) on December 4 and 5, please plan to park on neighboring streets outside of the work area. Paving work is weather dependent and may be rescheduled if conditions are not suitable.
Please travel slowly through the area and follow all posted signs and crew directions.
Remaining restoration activities
After backfilling and temporary paving of the intersection, crews will focus restoration efforts on Fruitland Landing. The park is anticipated to be reopened to the public after restoration is complete.
Final paving is weather dependent and will be scheduled at a later date during the next permitted paving window, which begins in mid-March. We will provide an update with more information on final paving and other remaining restoration when the work is scheduled.
|
|
What to expect:
- Approved work hours are 7 a.m. to 7 p.m. Monday to Saturday.
- All work will be performed in the public right-of-way.
- Noise, dust, and vibrations typical of an active construction project.
- Increased noise and vibrations during backfilling and compacting.
- Emergency vehicle access will be maintained.
- Garbage, recycling, composting, and mail service will be maintained.
- If services are interrupted, please call the project hotline at 425-305-3578.
- Construction schedules can change based on factors such as site conditions, weather, and material availability. Please visit the project website for updates.
|
|
Learn more about this project
|
|
|
|