Final paving and restoration activities planned on 97th Ave SE
as early as October 7
|
|
Expect single lane alternating traffic and driveway impacts |
|
Grinding the roadway
As early as October 7, crews will grind the roadway to create a flat surface for paving. Grinding is expected to be completed in one day. During this work, residents may hear increased noise and experience vibrations, and the roadway will be rough and unfinished until paving is complete.
Single lane alternating traffic will be in place along 97th Ave SE, and access for residents and vehicles will be maintained. Please travel slowly through the area and follow all posted signs and crew directions.
Paving the roadway
Paving will begin as early as October 16, about one week after grinding is complete. The work is expected to take one day, followed by a few hours of curing time. During paving, residents can expect single lane traffic. Once crews begin paving, they cannot stop or allow cars to drive on the newly paved roadway.
|
Parking advisory
During paving, driveways in the work area will be inaccessible for three to four hours while the pavement cures.
|
Map of work area along 97th Ave SE. Vehicle and resident access will be maintained. Please travel slowly through the area and follow all directions from posted signs and crews.
|
If you plan to leave your home during permitted hours (7 a.m. to 7 p.m.) on October 16, please plan to park on neighboring streets outside of the work area. If you have access concerns, please contact the Community Services team at 425-305-3578 or NMEsewer@kingcounty.gov.
|
|
What to expect:
- Approved work hours are 7 a.m. to 7 p.m. Monday to Saturday.
- All work will be performed in the public right-of-way.
- Noise, dust, and vibrations typical of an active construction project.
- Increase in noise and vibrations during grinding.
- Emergency vehicle access will be maintained.
- Garbage, recycling, composting, and mail service will be maintained.
- If services are interrupted, please call the project hotline at 425-305-3578.
- Construction schedules can change based on factors such as site conditions, weather, and material availability. Please visit the project website for updates.
|
|
Learn more about this project
|
|
|
|