|
Paving on Southeast 35th Place as early as mid-September
Some construction activities remain
|
|
Plans for paving and access to S.E. 35th Pl
Crews have been installing pipe in the roadway and constructing underground odor control and diversion structures in the cul-de-sac on S.E. 35th Pl. After finishing up pipe installation in the S.E. 35th Pl roadway, crews will backfill, restore, and pave the road.
Paving is expected to happen as early as the middle of September. During paving, residents can expect single lane traffic and temporary access impacts to driveways. We will email this listserv and update the project website when paving dates are confirmed. We will also share more details on the paving schedule and impacts to residents in the S.E. 35th Pl neighborhood. After paving is complete, crews will restore S.E. 35th Pl to two-way traffic. Residents will be able to access their homes from East Mercer Way.
Temporary access roads
Due to the location of work along the roadway, crews installed temporary detour roads for residents to access their homes. The temporary road off the cul-de-sac was removed in July. The temporary road off Frontage Road remains in place for residents on S.E. 35th Pl east of the cul-de-sac. This is to keep everyone safe while crews work on air vaults in the road and prepare the area for paving and restoration.
Remaining construction activities
Crews will continue be in the area to work on structures in the cul-de-sac and complete planting and other restoration activities along the roadway.
In addition, crews need to return at a later date to complete a water tie-in in the roadway. This is expected to take place on S.E. 35th Pl east of Briarwood Lane and may have traffic impacts. We will share more information once more details are known about that work.
Map of current work areas and traffic access on and adjacent to S.E. 35th Pl.
|
|
What to expect
- Permitted work hours are 7 a.m. to 7 p.m. Monday to Saturday.
- Work outside these hours will be done as approved by the City of Mercer Island.
- All work will be performed in the public right-of-way.
- Flaggers, traffic control signals, and single-lane alternating traffic may be used during work hours.
- Access to the Mercer Island Boat Launch will be maintained.
- Noise, dust, and vibrations typical of an active construction project.
- Emergency vehicle access will be maintained.
- Garbage, recycling, composting, and mail service will be maintained.
- If services are interrupted, please call the project hotline at 425-305-3578.
- Construction schedules can change based on factors such as site conditions, weather, and material availability. Please check the project website for updates.
|
|
Learn more about this project
|
|
|
|