Construction activities continue on West Armory Way and West Wheeler Street

header

August 2024

Construction activities continue on West Armory Way and West Wheeler Street

Expect to see crews and construction vehicles as early as August 5


Construction is ramping up on the Interbay Sewer and Odor Control Upgrade Project.

Over the past month, crews have been preparing the site for the new odor control facility. Crews have been clearing the land and putting up construction fencing.

Odor control facility with two tanks for air treatment.

Starting as early as next week and continuing through the summer, neighbors and businesses will see the crews performing the following activities:

  • Removing old pavement and dirt
  • Locating buried utilities
  • Installing storm drainpipe
  • Installing a new waterline

 

Figure 1: Example of an odor control facility.

To accommodate crews and construction vehicles there will be a full closure of the road at the end of the cul-de-sac on W. Armory Way. This closure is not expected to impact access for nearby neighbors to local businesses.


Map shows approximate location of work area on Armory Way and W Wheeler St.

Figure 2: Map of approximate work area and new odor control facility


What to expect

  • Approved work hours are 7 a.m. to 5 p.m. Monday to Thursday.
    • We will provide advance notice of any weekend or after-hours work.
  • Noise, dust, and vibrations typical of an active construction project.
  • Large construction equipment in the right of way until work is complete.
  • Jackhammers and saws for saw cutting and breaking pavement.
  • Crews using handheld surveying tools.
  • Construction schedules can change due to site conditions, weather, and material availability. Please check our project website for updates

During construction, access will be maintained for all emergency vehicles, garbage, recycling, composting, and mail services. If services are interrupted, please call the project hotline at 425-595-3452.

Please watch for equipment and crews in the area, maintain slow speeds to stay safe, and follow directions from crews.


For more information and project updates:

Los servicios de interpretación y traducción están disponibles para usted sin costo alguno. Si los necesita, comuníquese con Interbaysewer@kingcounty.gov, 425-595-3452.