East Lake Sammamish Trail Project Update
South Sammamish Segment A closing for construction
We will be closing the East Lake Sammamish Trail (ELST) from SE 43rd Way to SE 33rd Street starting in mid-December as crews work to pave and widen this segment of the trail.
Closing the trail in the construction zone allows crews the opportunity to safely conduct multiple activities at the same time and hastens completion of the project. For your safety and the safety of our construction crews, we will clearly mark the construction zone with orange fencing, signs, and barricades. A King County Sheriff's Deputy will be on site during construction. We anticipate that this segment will be closed for approximately one year.
Still looking to complete your ride or walk? East Lake Sammamish Parkway features bike lanes and sidewalks for people to travel around the closed stretch of trail.
Want to have an uninterrupted journey? Visit our new TrailFinder feature to locate other great trails near you!
How will the trail be improved?
- 12-foot-wide paved path with two-foot soft surface shoulders on each side
- Enhanced intersections, clear sight lines, improved drainage, and improved wildlife habitat
- Greater accessibility and safety for all trail visitors
Thank you for your patience during construction. Once developed, the ELST will complete the missing link in a 44-mile regional trail extending from Puget Sound in Ballard to the foothills of the Cascade Mountains.
What to expect during construction
- Increased activity and noise from construction crews, trucks, and equipment traffic along the trail corridor.
- Access to private properties will be maintained. King County will notify property owners when working near driveways.
- The contractor will provide flaggers to ensure trail neighbors can safely cross the trail to access homes, recreational properties, and businesses.
- Adjacent property owners are encouraged to remove as soon as possible any landscaping, fencing, or other items that are within the King County right-of-way and conflict with trail construction. Any remaining items that conflict with trail construction will be removed and disposed of by the contractor.
- The contractor will use construction best management practices to control dust, but some dust should be expected.
- Contractor work hours
- Weekdays, 7 a.m. to 7 p.m.
- Saturday, 9 a.m. to 6 p.m.
- No work on Sundays
Happy Holidays
This project is funded in part by the voter-approved 2014-2019 King County Parks, Trails and Open Space Replacement Levy. In this season of giving thanks, we'd like to express our appreciation for your support and patience as we move closer to completing this exciting trail project.
We wish you the best for the holiday season and a Happy New Year!
|
Contact Us
Questions during construction? Call the project hotline at 1-888-668-4886 or email us at ELST@kingcounty.gov.
We've updated the website, have a look! www.kingcounty.gov/eastlakesammamishtrail
|