Temporary bus stop relocations
Route 113 Northbound 36th Ave West & 179th St Southwest Stop Relocation
Due to construction for a new Swift Orange Line station, the northbound stop at 36th Avenue W and 179th Street SW in Lynnwood has been closed. We have installed a temporary bus stop approximately 300 feet north, across 179th Street SW. (Example of a temporary stop is pictured above.)
Throughout this project, we will continue to need to close bus stops for construction. We will install temporary bus stops near the previous bus stops. Riders can identify temporary stops by looking for signage or traffic cones on or near sidewalks.
To stay informed of temporary bus stop relocations, we encourage riders to sign up for Community Transit Rider Alerts. For construction-related concerns, call (425) 224-2441 or email swiftorangeconstruction@commtrans.org
|
Buses on Sunday schedule on Independence Day
All Community Transit service and Sound Transit buses to/from Snohomish County will operate a Sunday schedule on Independence Day, Monday, July 4. This includes:
- All Community Transit bus and DART paratransit service
- Sound Transit buses to/from Snohomish County
Customer Care phone lines and RideStore will be closed.
There will be no bus service to downtown Seattle. Sound Transit Route 512 will be the only bus going to Northgate.
Route schedules are available at communitytransit.org/Schedules. For help planning a trip, visit www.communitytransit.org/tripplanner, or contact Customer Care at (425) 353-RIDE (7433) prior to the holiday.
|
Edmonds College
Crews are continuing to make progress on the utility and sidewalk upgrades at Edmonds College. For the next few weeks, you can continue to expect digging for water utility upgrades and forming, pouring, and curing concrete sidewalks, curbs, and curb ramps.
A temporary bus stop platform has been installed on 68th Avenue West while crews work in the bus loop.
Pictured above: Crews have started upgrading and relocating utilities at Edmonds College
|
33rd Ave West & 188th St Southwest near Alderwood Mall
Crews continue to work on upgrades along 33rd Avenue West. This work includes potholing, storm drain installation, utility upgrades, and roadway and sidewalk upgrades.
Crews will work overnight during the weekend of July 8 – 10 to pour and cure concrete in this area. You can expect some construction lights and light noise during this work.
Pictured above: Crews are preparing the street for a concrete pad where buses will stop on 33rd Avenue West.
|
36th Ave West & Maple Road
Crews have started work along 36th Avenue West at Maple Road. This work will include digging (potholing) to identify and upgrade underground utilities and demolishing and upgrading sections of the street and sidewalk. Crews will work on both the northbound and southbound bus stops in this area. You can expect shifted lanes around work zones during construction.
Crews will work overnight during the weekend of July 8 – 10 to pour and cure concrete in this area. You can expect some construction lights and light noise during this work.
Pictured above: Due to the width of the road, crews may need to temporarily shift traffic around the traffic median. Please practice caution when traveling along 36th Avenue West.
|
McCollum Park
Crews have started preparing the McCollum Park Park and Ride for construction. Active construction is anticipated to begin as early as next week. The first phase of construction includes:
- Clearing the area south of the McCollum Park Athletic Field in preparation for a new parking lot
- Installing the foundation (subgrade) for the new parking lot
- Pouring and curing the new parking lot
- Temporarily relocating ADA parking spots to the new parking lot once completed
- Adding a new temporary bus loading zone south of the existing BMX track
Construction is expected to continue into 2023. Once the new temporary parking lot and bus loading zone has been installed, crews will remain in the area to begin construction for the main parking lot, bus zones, and to complete work on Dumas Road. The final design for the McCollum Park Park and Ride can be found on our project website under “Terminal Stations.”
196th St and Hwy 99
As part of this project, several utility companies will be completing upgrades in the project corridor. Crews working for Zayo – a telecommunications utility provider – have started working at the corner of 196th Street SW and Highway 99. This work will take place overnight and will continue for several weeks.
Stay Informed
During construction, we will occasionally send out email updates to share updates about construction, upcoming traffic impacts, and more information about the project.
If you are located near a planned Swift station, please take a moment to fill out our construction survey. We may be reaching out to neighbors if there are any anticipated impacts prior to construction starting at each location.
Have questions during construction? Please call (425) 224-2441 or email swiftorangeconstruction@commtrans.org.
|

You are receiving this email because you have expressed interest in Community Transit’s Swift bus rapid transit (BRT) network, or you have signed up for email alerts for a route near an existing or future Swift line.
|