Town of Leesburg, Virginia Lawson Road Pedestrian Crossing Update
Town of Leesburg, Virginia sent this bulletin at 10/19/2026 03:54 PM EDTHaving trouble viewing this email? View it as a Web page. ![]()
You are subscribed to Lawson Road Pedestrian Crossing for Town of Leesburg, Virginia. This information has recently been updated, and is now available.
As of October 19, 2026 - The contractor returned to the project site on Monday, October 19 and began repairs to the washed-out areas adjacent to the pedestrian bridge crossing. We anticipate that this work will take approximately 3–4 weeks to reach substantial completion.
Once the work is substantially complete, the Town will conduct a final inspection and prepare a punch list of any remaining items for the contractor to address before the Town formally accepts the bridge. This final step is expected to take up to an additional four weeks.
Following completion of the punch list and formal acceptance by the Town, the bridge will be officially opened to the public.
We appreciate your patience as we work to complete the streambank repairs and look forward to opening the project to the public by early 2027.