 In this episode, we visit Oak Ridge, Paducah, and Portsmouth to see how federal sites are becoming American Energy Hubs. From $15 billion in nuclear projects and 10,000 new jobs in Oak Ridge to new investment in Paducah and ongoing transformation at Portsmouth, see how cleanup is creating opportunities for the next generation while strengthening America’s energy future.
Crews Demolish ORNL’s Historic Isotope Row
 Crews completed demolition of all 10 buildings along Isotope Row, overcoming tight working conditions and the challenges of working alongside active laboratory operations. This major cleanup milestone reduces risks and helps prepare the site for future research missions.
Oak Ridge Beats Goal for U-233 Processing
 Oak Ridge beat its goal for the highest-priority cleanup project at Oak Ridge National Laboratory. Contractor Isotek processed 62 canisters of uranium-233 for safe transportation and disposal during the fiscal year that recently ended, surpassing its 50-canister goal. This important and challenging work is reducing risk while also making some material available to support medical treatments.
Upgrades Expand Waste Processing Capabilities
The Transuranic Waste Processing Center (TWPC) recently remodeled its cask processing enclosure (CPE) to handle large waste boxes from deactivation and demolition work at Oak Ridge National Laboratory and Y-12 National Security Complex. Workers modified the ventilation system and installed new cameras, monitoring software and a drum crusher. By repurposing space and giving crews more tools, TWPC is expanding its processing capabilities and advancing cleanup across the Oak Ridge Reservation.
|
Crews Transform White Wing Scrap Yard
 Crews are set to remediate soil across a portion of the White Wing Scrap Yard, a Cold War-era disposal site for contaminated equipment and debris, helping reduce environmental risk and prepare land for future use. Workers already cleared 39 acres of trees and packaged over 500 bags of legacy soil after excavating several acres of land in the footprint’s north boundary.
|
|
|
|