CSMS# 13-000395 - ACE Development and Deployment Schedule and Stakeholder Backlog Posted on CBP.GOV

You are subscribed to Rail Manifest for U.S. Customs and Border Protection. This information has recently been updated, and is now available.

08/08/2013 12:43 PM EDT

Rail Manifest

CBP has posted the most current ACE Development & Deployment Schedule and Stakeholder Backlog to cbp.gov for your reference. The deployment schedule is based on the development plans for completing all core trade functionality in ACE within the next 3 years. The plan proposes 7 major deployments over the coming 3 years. The plan now includes the following mandatory dates:

• May 1, 2015: Mandated use of Manifest – All electronic export and import manifest data must be transmitted via ACE.

• November 1, 2015: Mandated use of Cargo Release – All data associated with the release of cargo, including PGA interactions, must be transmitted via ACE.

• October 1, 2016: Mandated use of ACE.



The 3 documents, development schedule, deployment schedule and stakeholder backlog, have been posted to CBP.gov at the link below.