Work on Gedling Access Road accelerates into 2020

nottinghamshire county council
email me

Gedling Access Road

facebooktwitteryoutube

Bookmark and Share Having trouble viewing this email? View it as a Web page.

Welcome to this first email bulletin about the Gedling Access Road which you previously subscribed to. This bulletin will keep you updated on all the progress and major developments until the new road is in operation.

The Gedling Access Road is a new 3.8km single carriageway that will link the B684 Mapperley Plains to the A612 Trent Valley Road. 

Once complete, the new road will significantly reduce traffic travelling through Gedling Village and will help to unlock the potential of the former Gedling Colliery/Chase Farm site.

GAR image

Work on Gedling Access Road accelerates into New Year

GAR New Year work

Main construction work on the Gedling Access Road is scheduled to begin on 6 January 2020 for 18 months and will mark the beginning of sustainable redevelopment in the area for future generations.

The link from the B684 Mapperley plains to the A612 Trent Valley Road is expected to open to traffic in Summer 2021 following the approval of the construction timetable at Nottinghamshire County Council’s Communities and Place Committee today (5 December).

Read Story

Want to find out more about the Gedling Access Road?

GAR poster image

We are holding two public events to give you the opportunity to find out more about the construction of the road and the people who will be working on it. 

The team will be on hand to answer your questions and give you more details about what to expect from the construction and the benefits of the road. 

Come along to one of the following events:

Monday 9 December, 2pm - 6pm
3rd Woodthorpe Scount Hut, NG3 5RJ

Wednesday 11 December, 5pm - 8pm
Carlton le Willows Academy, NG4 4AA

View the Gedling Access Road timeline

GAR timeline

A number of road closures will be required and regular updates will be issued to minimise disruption.

Here is what the 18 months of construction will look like:

January 2020 - June 2021 - Main works will take place to construct the Gedling Access Road. 

July 2021 - September 2021 - Works to take place on Arnold Lane once the new road is open requiring the closure of the Arnold Lane/Mapperley Plains/Plains Road junction

October 2021 - All works completed

As the project continues, you will be able to find out more information about the above stages on our website, social media channels and this bulletin. If you know someone who would like to find out more about the Gedling Access Road, why not recommend that they sign up for updates straight into their inbox? 

Read more

Get in touch about the Gedling Access Road

Did you know that there are a number of ways you can get in touch with us about the Gedling Access Road? 

Our team are happy to answer any questions you may have and you can contact them on: 

  • Email: gar@viaem.co.uk
  • Telephone: 0300 500 8080 between 8am and 6pm Monday to Friday 