Our contractors Balfour Beatty are in the last few weeks of site works on our A14 and M11 programme of essential works. The main work over the last two weeks has been the replacement of the bridge joints on the A1307 Huntingdon Road Bridge in both directions. This work was completed over a weekend and a series of overnight midweek full carriageway closures has gone well and has been completed ahead of schedule.
Next week we are working on the A14 westbound between junction 24 and 23 to replace the existing bridge joint, traffic loop counter commissioning work on the A14 eastbound junction 27A, 33 and also on the M11 junction 13 entry slip road north and southbound junction 13 exit slip road. We are also working on the A1307 to resurface the central reservation and seed the verges. In addition to this work we have surfacing work on the Cambridge Road Madingley.
Here's the current schedule of works that Balfour Beatty are carrying out on behalf of Highways England. Remember schedules may change at short notice, for example due to bad weather.
Queries? Contact Highways England on 0300 123 5000 or info@highwaysengland.co.uk.
Know someone who'd like to receive these notifications? They can subscribe at www.highways.gov.uk/A14roadworks_subscribe.
Date
|
Location of works |
Type of works |
Diversion |
Thurs 18th August (day time off peak 9.30am-4pm) |
Cambridge Road Madingley full carriageway closure north and southbound. |
Verge seeding and surfacing |
Church Lane and the A1303 Madingley Road |
Thurs 18th August (day time off peak 9.30am-3.30pm) |
A1307 outbound lane 1 closures. |
Verge seeding |
N/A
|
Fri 19th to 25th August (night time off peak 8pm-6am)
|
A1307 inbound full carriageway closure across the Huntingdon Road Bridge. |
Bridge joint replacement |
Traffic inbound will be diverted via the A14 eastbound to junction 32 Histon, onto the B1049 Histon/Cambridge Road and back onto the A1307. |
Fri 19th to 25th August (night time off peak 8pm-6am) |
A1307 outbound lane 2 closure across the Huntingdon Road Bridge. |
Bridge joint replacement (lane closed for safety) |
N/A |
Mon 22nd for 4 nights (night time off peak 8pm-6am) |
A14 westbound junction 24-23 full carriageway closure. |
Bridge joint replacement |
The A1195 to Caxton, A428 westbound to Wyboston, A1 northbound to Brampton Hut and back onto the A14, traffic wanting Alconbury and Huntingdon will be signed to follow the A14 eastbound back to junction 24 Spittles. |
Mon 22nd August (night time off peak 8pm-6am)
Provisional subject to sub-contractor availability
|
A14 eastbound junction 27 Fenstaton to junction 28 Swavesey lane 1 closure. |
Traffic loop counter commissioning |
N/A |
Mon 22nd August (night time off peak 8pm-6am) for up to 2 nights
Provisional subject to sub-contractor availability
|
A14 eastbound junction 32 Kings Hedges to junction 33 Milton lane 1 closure. |
Traffic loop counter commissioning |
N/A |
Tues 23rd August (night time off peak 8pm-6am) for up to 2 nights
Provisional subject to sub-contractor availability
|
M11 northbound junction 14 Girton exit slip and the A14 junction 31 north to east Girton Cloverleaf loop full carriageway closure. |
Traffic loop counter commissioning |
The A14 westbound to junction 30 Oakington, the A14 eastbound to junction 31 Girton. |
Weds 24th August (night time off peak 10pm-5am) for up to 2 nights
Provisional subject to sub-contractor availability
|
M11 northbound junction 12 to 13 lane 1 closure with junction 13 exit slip road full carriageway closure.
(dependent on M11 junction 14 Girton exit slip and A14 junction 31 Girton Cloverleaf loop full carriageway works being completed)
|
Traffic loop counter commissioning |
The A14 westbound to junction 30 Oakington, the A14 eastbound to junction 32 Milton, the A14/A428 westbound to Hardwick and the A428 eastbound to Madingley A1303. |
Weds 24th August (night time off peak 10pm-5am) for up to 2 nights
Provisional subject to sub-contractor availability
|
M11 southbound junction 13 entry slip road |
Traffic loop counter commissioning |
The A1303 Madingley road to the A1134, the A1134 to the junction with the A603 Barton Road, the A603 to the M11 junction 12 southbound entry slip road. |
Tues 30th August for up to 6 nights (night time off peak 8pm-6am, weekday nights only) |
A14 westbound junction 24-23 full carriageway closure |
Bridge joint replacement |
The A1195 to Caxton, A428 westbound to Wyboston, A1 northbound to Brampton Hut and back onto the A14, traffic wanting Alconbury and Huntingdon will be signed to follow the A14 eastbound back to junction 24 Spittles. |
|
Thank you for signing up to stay informed about the A14 and M11 Essential works. We'll do our utmost to complete these works quickly, avoid disturbance and keep noise to a minimum.
Once complete, the work will result in a smoother and safer A14, better bridges, and clearer directions to Addenbrookes Hospital.