Edwards Ranch Pump Station Backup Power and Electrical Improvements

The Edwards Ranch Pump Station requires replacement of aging electrical switchgear and motor as well as backup generators. The improvements are vital to keep the pump stations operating if there is another deep freeze similar to the one in February 2021.

This project also includes the replacement of a 36-inch to 42-inch in diameter concrete water line immediately in front of the pump station.

The pump station is located just north of the intersection of Overton Park Drive W and Bellaire Drive South.

This capital improvement project is in Fort Worth Council District 3. Construction may impact the Tanglewood neighborhood association.

Meeting Details

  • Monday, April 25 at 6 p.m.
  • Tanglewood Elementary School
  • 3060 Overton Park Drive West
  • Fort Worth, TX 76109

Contact


Mejoras eléctricas y de energía de respaldo en la Estación de Bombeo Edwards Ranch

La Estación de Bombeo Edwards Ranch necesita el reemplazo del equipo eléctrico y motores, así como la instalación de generadores de respaldo. Las mejoras son vitales para mantener en funcionamiento las estaciones de bombeo en caso de que haya otro congelamiento similar al evento de febrero de 2021.

Este proyecto también incluye el reemplazo de la tubería de agua hecha de concreto de 36 a 42 pulgadas de diámetro justo frente a la estación de bombeo.

La estación de bombeo está ubicada justo al norte de la intersección de Overton Park Drive W y Bellaire Drive South.

Este proyecto de mejoras capitales se encuentra en el Distrito Municipal 3 de Fort Worth. La construcción podría afectar a la asociación de vecinos Tanglewood.

Detalles de Junta 

  • Jueves 25 de abril a las 6 p.m.
  • Escuela Primaria Tanglewood
  • 3060 Overton Park Drive West
  • Fort Worth, TX 76109

Contacto