I-35 from FM 3009 to FM 1518
Northbound
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp, and entrance ramp of northbound I-35 from Evans Road to Roy Richard Drive (FM 3009) for barrier work. Traffic should use next available ramps.
Southbound
- Through Saturday, January 25, long-term closure (24/7). Right lane closure on the southbound frontage road of I-35 from FM 3009 to Schertz Parkway for roadway work.
- Sunday, January 5, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road and exit ramp from Schertz Parkway to Corporate Drive (FM 1518) for column and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple mainlane closures (3), and entrance ramp closure, and exit ramp closure of southbound I-35 from Roy Richard Drive (FM 3009) to Schertz Parkway for column and cap work. Traffic should use next entrance and exit ramps.
I-35 from FM 1518 to Loop 1604
Northbound
- Through Saturday, August 2, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Forum Parkway to Forum Access Road for construction work.
- Through Monday, May 5, long-term closure (24/7). Exit ramp closure on northbound I-35 to Evans Road for construction work.
- Sunday, January 5, until Tuesday, January 7, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Access Road and full closure of northbound I-35 collector ramp at Loop 1604 interchange for bridge column and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Tuesday, January 7, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge column and cap work. Traffic should use next exit and entrance ramps.
- Sunday, January 5, until Tuesday, January 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Forum Parkway to Forum Access Road for bridge cap and column work. Traffic should follow detour signs.
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for bridge structure work. Traffic should follow detour signs.
- Monday, January 6, 9 p.m. to 5 a.m. Left lane closure on the northbound frontage road of I-35 from Olympia Parkway to Evans Road for bridge work.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Olympia Parkway for bridge column and cap work. Traffic should follow detour signs.
- Tuesday, January 7, 9 p.m. to 5 a.m. Left lane closure on the northbound frontage road of I-35 from Olympia Parkway to Evans Road for bridge work.
Southbound
- Through Sunday, May 25, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Forum Parkway to Old Austin Road for bridge and roadway work.
- Sunday, January 5, until Tuesday, January 7, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Access Road and full closure of northbound I-35 collector ramp at Loop 1604 interchange for bridge column and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Tuesday, January 7, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge column and cap work. Traffic should use next exit and entrance ramps.
- Sunday, January 5, until Tuesday, January 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Forum Parkway to Forum Access Road for bridge cap and column work. Traffic should follow detour signs.
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for bridge structure work. Traffic should follow detour signs.
- Monday, January 6, 9 p.m. to 5 a.m. Left lane closure on the northbound frontage road of I-35 from Olympia Parkway to Evans Road for bridge work.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Olympia Parkway for bridge column and cap work. Traffic should follow detour signs.
- Tuesday, January 7, 9 p.m. to 5 a.m. Left lane closure on the northbound frontage road of I-35 from Olympia Parkway to Evans Road for bridge work.
Loop 1604 Interchange
Northbound
- Sunday, January 5, until Tuesday, January 7, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at the Loop 1604 interchange for bridge column and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at Loop 1604 interchange, northbound I-35 frontage road at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for bridge structure work. Traffic should follow detour signs.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 collector ramp at I-35 interchange, northbound I-35 connector ramp to westbound Loop 1604 mainlanes, and southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at the Loop 1604 interchange for column cap setting. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of northbound I-35 connector ramp to westbound Loop 1604 mainlanes for column cap setting. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 connector ramp to northbound I-35 mainlanes for column cap setting. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at the Loop 1604 interchange for drilled shaft work. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at Loop 1604 interchange, northbound I-35 bypass bridge at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for column, cap, and bridge beam work. Traffic follows detour signs.
Southbound
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure on westbound I-35 collector ramp and northbound I-35 to westbound Loop 1604 connector ramp, full closure on southbound I-35 to westbound Loop 1604 connector ramp, full closure on eastbound frontage road from entrance ramp to IKEA-RBFCU Parkway and full closure of northbound and southbound lanes of IKEA-RBFCU Parkway at Loop 1604, exit ramp closure to Olympia Parkway for deck, overhangs, column work.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, westbound Loop 1604 collector ramp at I-35 interchange, northbound I-35 connector ramp to westbound Loop 1604 mainlanes, southbound I-35 connector ramp to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway exit ramp to IKEA-RBFCU Parkway and northbound and southbound lanes of IKEA-RBFCU Parkway at Loop 1604 for bridge column, cap and deck work. Traffic should follow detour signs.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector ramp at I-35 interchange and southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Sunday, January 5, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of southbound Loop 1604 frontage road from IKEA-RBFCU Parkway to Pat Booker Road, eastbound Loop 1604 connector ramp to southbound I-35 mainlanes, and southbound I-35 collector ramp closure at Loop 1604 interchange for wall demolition, bridge column, and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 connector ramp to southbound I-35 mainlanes for bridge deck work. Traffic should follow detour signs.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of southbound I-35 connector ramp to westbound Loop 1604 and alternating mainlane closures (2) of southbound I-35 at Loop 1604 interchange for column and cap work. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of southbound I-35 collector ramp at Loop 1604 interchange, southbound I-35 connector ramp to westbound Loop 1604 mainlanes, and southbound I-35 frontage road for bridge deck work. Traffic should follow detour signs.
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector ramp at the I-35 interchange, and southbound I-35 connector ramp to eastbound Loop 1604 mainlanes for barrier work. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on westbound I-35 collector ramp at Loop 1604 interchange, northbound I-35 to westbound Loop 1604 connector ramp, southbound I-35 to westbound Loop 1604 connector ramp, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway exit to IKEA-RBFCU Parkway intersection, IKEA-RBFCU Parkway intersection at Loop 1604, and full closure of northbound I-35 exit ramp to Olympia Parkway for column cap setting. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of southbound I-35 connector ramp to eastbound Loop 1604 mainlanes and eastbound Loop 1604 mainlanes from IKEA-RBFCU Parkway to Pat Booker Road for column cap setting. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 connector ramp to southbound I-35 mainlanes for column cap setting. Traffic should follow detour signs.
- Tuesday, January 7, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of southbound I-35 connector ramp to eastbound Loop 1604 mainlanes for column cap setting. Traffic should follow detour signs.
- Tuesday, January 7, until Thursday, January 9, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 connector ramp to southbound I-35 mainlanes for bridge structure work. Traffic should follow detour signs.
Loop 1604 from I-35 Interchange to Nacogdoches Road
Eastbound
- Through Monday, March 31, long-term closure (24/7). Left lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Boulevard for construction.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Lookout Road to Pat Booker Road for bridge beam setting. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Lookout Road to Pat Booker Road for bridge beam setting. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector ramp at I-35 interchange and full closure of eastbound Loop 1604 entrance ramp from Lookout Road to IKEA-RBFCU Parkway for bridge column and cap work. Traffic should follow detour signs.
- Monday, January 6, until Thursday, January 9, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Nacogdoches Road to Pat Booker Road for bridge deck work. Traffic should follow detour signs.
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Alternating mainlane closures of eastbound Loop 1604 from Nacogdoches Road to Pat Booker Road for bridge column work.
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 mainlanes from Pat Booker Road to Gateway Boulevard, westbound Loop 1604 collector ramp at I-35 interchange, southbound I-35 collector ramp at Loop 1604 interchange, and northbound I-35 connector ramp to westbound Loop 1604 mainlanes for bridge deck work. Traffic should follow detour signs.
- Wednesday, January 8, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Gateway Boulevard to Pat Booker Road, eastbound Loop 1604 collector ramp at I-35 interchange, and southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
Westbound
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 collector ramp at I-35 interchange for column cap setting. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Alternating mainlane closures of westbound Loop 1604 from Pat Booker Road to Nacogdoches Road for bridge deck and barrier work.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 mainlanes from Pat Booker Road to Nacogdoches Road for bridge deck work. Traffic should follow detour signs.
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of Lookout Road and turnarounds at Loop 1604 intersection for bridge deck work. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road from Gateway Boulevard to Gateway Place for bridge deck work. Traffic should follow detour signs.
I-35 from Loop 1604 to Toepperwein Road
Northbound
- Through Monday, February 3, long-term closure (24/7). Full closure on I-35 northbound collector exit ramp and left lane closure on I-35 northbound frontage road from Pat Booker Road to Loop 1604 for bridge work.
- Through Monday, February 3, long-term closure (24/7). Entrance ramp closure from Shin Oak Drive to Pat Booker Road for bridge work.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, exit ramp, and entrance ramp from Pat Booker Road to Loop 1604 for bridge column and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Wednesday, January 8, 9 p.m. to 5 a.m. Full closure of Pat Booker Road at I-35 intersection and northbound I-35 exit ramp to Pat Booker Road for bridge structure work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for column and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Wednesday, January 8, 9 p.m. to 5 a.m. Multiple mainlane closures (3), exit ramp of northbound I-35 from I-35 Access Road bridge near Shin Oak Drive to Forum Parkway for bridge column and cap work. Traffic should use next exit and entrance ramps.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on northbound I-35, multiple lane closures (2) on northbound I-35 frontage road and exit ramp closure from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
- Monday, January 6, 9 p.m. to 5 a.m. Full closure of I-35 Access Road bridge near Shin Oak Drive at I-35 for deck work. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road near Shin Oak Drive to Forum Parkway for bridge structure work.
Southbound
- Through Monday, June 30, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Pat Booker Road to Toepperwein Road for bridge deck work.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
I-35 from Toepperwein Road to O’Connor Road
Northbound
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, exit ramp closure and entrance ramp closure from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound mainlanes, multiple lane closures (2) on northbound I-35 frontage road and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, January 5, 9 p.m. to 5 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on northbound frontage road and exit ramp of I-35 from Judson Road to Toepperwein Road for bridge beam setting. Traffic should follow detour signs.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Multiple lane (3) closure on northbound mainlanes of I-35 from Judson Road to Toepperwein Road for bridge beam setting.
Southbound
- Through Friday, January 10, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Crownpoint Drive for construction work.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Toepperwein Road to Judson Road for bridge deck work.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Judson Road to O’Connor Road for drilled shaft, column, and cap work.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp closure from Crownpoint Drive to O’Connor Road for cap form erection work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
I-35 from O’Connor Road to Thousand Oaks Drive
Northbound
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and full closure of Starlight Terrace at I-35 intersection for drainage and drilled shaft work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Weidner Road to O’Connor Road for drainage and drilled shaft work.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road and exit ramp closure from Thousand Oaks Drive to Weidner Road for drainage and drilled shaft work.
Southbound
- Through Saturday, January 25, long-term closure (24/7). Right lane closure on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for bridge work.
- Through Thursday, May 22, long-term closure (24/7). Entrance ramp closure on southbound I-35 from O’Connor Road for bridge work.
- Sunday, January 5, until Friday, January 10, 9 a.m. to 3 p.m. Right turn lane closure on southbound frontage road of I-35 at Weidner Road and right lane closure on westbound Weidner Road from southbound frontage road of I-35 to Weidner Road for utilities work.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, entrance ramp closure, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from O’Connor Road to Weidner Road for drilled shaft, column, and cap work.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from O’Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, January 5, until Friday, January 10, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap form erection work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure on southbound frontage road, entrance ramp closure, and exit ramp closure of I-35 from Weidner Road to Thousand Oaks Drive for column work. Traffic should follow detour signs.
I-35 from Thousand Oaks Drive to I-410 North Interchange
Northbound
- Through Tuesday, January 28, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Randolph Boulevard to Starlight Terrace for bridge work.
Southbound
- Through Tuesday, April 1, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
- Through Saturday, February 1, long-term closure (24/7). Southbound to northbound turnaround closure at Thousand Oaks for construction work.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at I-35 and Thousand Oaks Drive for column, and cap work. Traffic should follow detour signs.
I-410 North Interchange
Northbound
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of northbound I-35 connector ramp to westbound I-410 mainlanes and entrance ramp closure from Randolph Boulevard to the mainlanes of westbound I-410 for bridge deck and cap work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of eastbound mainlanes I-410 to northbound mainlanes I-35 connector ramp and full closure of northbound frontage road exit ramp closure Crestway Drive for cap work. Traffic follows detour signs.
Southbound
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of eastbound I-410 connector ramp to southbound I-35 mainlanes for bridge deck work. Traffic should follow detour signs.
I-410 North from I-35 Interchange to Starcrest Drive
Westbound
- Through Tuesday, April 1, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of exit ramp from westbound I-410 mainlanes to southbound Austin Highway (Loop 368) for cap work. Traffic should use next exit ramp.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of eastbound I-410 frontage road to westbound frontage connector ramp from Austin Highway (Loop 368) to Perrin Creek, southbound I-35 frontage road from Randolph Boulevard to Perrin Creek and northbound I-410 frontage road to westbound I-410 frontage road at Perrin Creek for cap work. Traffic should use detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of entrance ramp of westbound I-410 frontage road from Perrin Creek to Perrin Beitel and exit ramp closure to Austin Highway (Loop 368) from southbound I-35 connector ramp to westbound I-410 mainlanes for cap work. Traffic should follow detour signs.
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of westbound I-410 frontage road and exit ramp from Perrin Creek to Perrin Beitel, and connector ramp closure from northbound Austin Highway (Loop 368) to westbound I-410 frontage road for bridge deck work. Traffic should follow detour signs.
I-410 North from Starcrest Drive to Nacogdoches Road
Eastbound
- Wednesday, January 8, until Saturday, January 11, 9 p.m. to 5 a.m. Exit ramp closure on eastbound I-410 mainlanes to Starcrest Drive for traffic shift work. Traffic should use previous exit and entrance ramps.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (2) and entrance ramp closure on eastbound I-410 mainlanes from Quail Creek Drive to Perrin Beitel for striping and barrier work.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Multiple lane closures (3) and entrance ramp closure on eastbound I-410 mainlanes from Harry Wurzbach Road to Quail Creek Drive for striping and barrier work.
I-35 from I-410 North Interchange to Walzem Road
Southbound
- Sunday, January 5, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure of southbound I-35 connector ramp to westbound I-410 mainlanes, Randolph Boulevard at I-35 intersection and southbound I-35 frontage road from Randolph Boulevard to Fratt Road for cap work. Traffic should follow detour signs.
- Monday, January 6, until Saturday, January 11, 9 p.m. to 5 a.m. Full closure on southbound frontage road, exit ramp, and entrance ramp of I-35 from Randolph Boulevard to Walzem Road for deck work. Traffic should follow detour signs.
I-35 from Walzem Road to Eisenhauer Road
Northbound
- Friday, January 10, 11 p.m. to 7 a.m. Multiple lane closures (2) on northbound I-35 frontage road from Eisenhauer Road to Galahad Drive for drilled shaft work.
- Friday, January 10, 11 p.m. to 7 a.m. Right lane closure on northbound I-35 mainlanes from Eisenhauer Road to Galahad Drive for drilled shaft work.
- Friday, January 10, 11 p.m. to 7 a.m. Exit ramp closure on northbound I-35 mainlanes to Walzem Road for drilled shaft work. Traffic should use prior exit ramp.
- Saturday, January 11, 9p.m. to 8 a.m. Multiple lane closures (2) on northbound I-35 frontage road from Eisenhauer Road to Galahad Drive for drilled shaft work.
- Saturday, January 11, 9p.m. to 8 a.m. Right lane closure on northbound I-35 mainlanes from Eisenhauer Road to Galahad Drive for drilled shaft work.
- Saturday, January 11, 9p.m. to 8 a.m. Exit ramp closure on northbound I-35 mainlanes to Walzem Road for drilled shaft work. Traffic should use prior exit ramp.
I-35 from Eisenhauer Road to Rittiman Road
Northbound
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Left lane closures on northbound I-35 frontage road from Rittiman Road to Center Park Boulevard for striping work.
Southbound
- Monday, January 6, until Wednesday, January 8, 9 p.m. to 5 a.m. Southbound to northbound turnaround closure at Rittiman Road for striping work.
I-35 from Rittiman Road to I-410 South Interchange
Southbound
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Multiple right lane closures (2) on southbound I-35 mainlanes from Rittiman Road to Petroleum Drive for drilled shaft work.
- Friday, January 10, 11 p.m. to 7 a.m. Multiple right lane closures (2) on southbound I-35 mainlanes from Rittiman Road to Petroleum Drive for drilled shaft work.
I-410 South from I-35 to Binz Engleman Road
Northbound
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Multiple lane closures (2) on northbound and southbound I-35 mainlanes from George Beach Avenue to Walzem Road and on I-410 from Binz Engleman Road to Space Center Drive for crack seal work.
- Monday, January 6, until Friday, January 10, 9 p.m. to 5 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
- Friday, January 10, 11 p.m. to 7 a.m. Multiple lane closures (2) on northbound and southbound I-35 mainlanes from George Beach Avenue to Walzem Road and on I-410 from Binz Engleman Road to Space Center Drive for crack seal work.
- Friday, January 10, 11 p.m. to 7 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
OTHER LANE CLOSURES
- For your information, there are other lane closures underway within the I-35 NEX project this week, but they are not expected to affect traffic or create notable delays.
|