 Current traffic impacts
-
Oxbow Drive/Altman Road intersection 24/7 closure through October 29 and from November 2-25 and November 30-December 24, 2026: Full closure of the intersection. Through traffic will be detoured to Lusted and Hosner roads. Intersection closure may extend through January 2027.
-
Dodge Park Boulevard (Cottrell Road to about 1500 feet east of intersection) through October 31, 2026: Single-lane with flagging during work hours. After work hours, normal traffic will resume.
-
Cottrell Road to Lusted Road, Hosner Road, and Oxbow Drive through January 2027: Expect increased haul truck traffic on this route as clean fill is transported to a fill site on Oxbow Drive east of the Oxbow/Altman intersection.
-
Bluff Road (at Proctor Road and 362nd Avenue intersection) through November 30, 2026: Intermittent single-lane restriction with two-way flagging Mon.-Sat. between 8:15 a.m.-2:15 p.m.
-
Altman Road (between Oxbow Drive and Pipeline Road) between October 30-November 1, 2026: Daytime closure with one lane of south-only traffic outside work hours.
Other work happening the week of October 26
Staff will be at the project work sites during shift hours to perform various tasks. Work hours will be between 7 a.m. and 6 p.m., Monday through Saturday.
Filtration facility site activities include:
- Ongoing construction traffic traveling to and from the site, including concrete trucks, soil off hauling, and bussing for craftworkers
- Delivering equipment and materials to the site
- Placing concrete for treatment process areas and buildings
- Installing roofing and siding for buildings
- Installing new water pipeline at the site
- Ongoing stormwater management and erosion control
- Lighting for safety and maintenance activities
- As needed street sweeping
Emergency access road activities include:
- Installing new water line in the access road
Raw water tunnel/pipeline site activities include:
- Excavating two 1,245-foot pipeline tunnels and installing new pipeline in the Water Bureau's easement between Lusted Road and the facility site
- Ongoing stormwater management and erosion control
- Noise and vibration during work hours
Finished water pipeline site activities include:
- Delivering equipment and materials to the work areas
- Installing new water pipeline on the south shoulder of Dodge Park Boulevard
- Backfilling and paving work area at the Oxbow Drive and Altman Road intersection
- Ongoing stormwater management and erosion control
- As needed street sweeping
Finished water intertie site activities include:
- Excavating and preparing to install pipe
- Ongoing stormwater management and erosion control
Work schedules are subject to change depending on weather and other field conditions.
Upcoming traffic impacts
Please note that some planned traffic restrictions are pending county approval.
-
Dodge Park Boulevard (east of Cottrell Road intersection) intermittent single-lane restriction with two-way flagging while tree work is occurring—estimated November 2-4, 2026
-
Dodge Park Boulevard (between Altman Road and Cottrell Road) single-lane restriction with flagging during work hours—estimated November 2-30, 2026
-
Cottrell Road (between Carpenter Lane and Bluff Road) intermittent two-way flagging while tree work is occurring—estimated mid-November 2026
-
Altman Road/Pipeline Road intersection and Altman Road (between Oxbow Drive and Pipeline Road) 24/7 closure—late November 2026-July 2027
Bull Run Filtration: neighbor update meeting (October 2026)
At the October 8 meeting, community members heard an update on pipeline and facility construction for the Bull Run Filtration Project.
Visit the October 8 Neighbor Update meeting webpage to see the meeting presentation and recording.
Bull Run Filtration: coffee with the contractor
We will host an informal drop-in session where project neighbors can chat with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There is no presentation, so stop in anytime between 9 and 10:30 a.m.
Date: Thursday, November 12, 2026
Time: 9-10:30 a.m. (drop in)
Location: Multnomah County Grange #71, 30639 SE Bluff Road, Gresham
Can't make it this time? Join us for the in-person Coffee with the Contractor in DecemberCoffee with the Contractor in December.
|