Traffic impacts
-
Dodge Park Boulevard (between Altman Road and Cottrell Road) October 1-31: Local access only 24/7 road closure with signed detours for through traffic to use Lusted Road or Bluff Road. Local residents, postal and garbage services, school buses, emergency vehicles, and farm equipment will have modified access.
-
Dodge Park Boulevard (east of Cottrell Road) October 1-31: Single-lane restriction with flagged two-way traffic during road improvements.
-
Dodge Park Boulevard/Altman Road intersection October 30: Single-lane restriction with flagged two-way traffic during pavement striping.
Traffic impacts coming up
- Lusted Road (near county line) single-lane restriction with two-way flagging during work hours — estimated November 3-19, 2025
- Altman Road/Lusted Road intersection local access only closure with one-way westbound traffic outside work hours on Lusted Road and one-way northbound traffic outside work hours on Altman Road—estimated November 6-December 12, 2025
- Lusted Road (near county line) single-lane restriction with 24/7 temporary signals to manage two-way traffic flow — estimated November 20, 2025-April 30, 2026
- Cottrell Road (between Dodge Park Boulevard and Lusted Road) local access only closure with one-way northbound traffic outside work hours—estimated December 1, 2025-May 1, 2026
- Lusted Road (between Altman Road and west of Hosner Road) local access only closure with one-way westbound traffic outside work hours— estimated December 13, 2025-May 15, 2026
Other work happening the week of October 27
Staff will be at the project work sites during shift hours to perform various tasks. Work hours will be between 7 a.m. and 6 p.m., Monday through Saturday.
Filtration facility site activities include:
Finished water pipeline site activities include:
- Installing new water pipeline connections across Dodge Park Boulevard
- Receiving and installing pipeline in City easement between Lusted Road and Dodge Park Boulevard
- Ongoing stormwater management and erosion control
- As needed street sweeping
Finished water intertie site activities include:
- Installing shoring for intertie building located off Lusted Road
- Occasional flagging near construction entrance
- Ongoing stormwater management and erosion control
Raw water tunnel/pipeline site activities include:
- Excavating raw water pipeline tunnel
- Occasional flagging near construction entrance
- Ongoing stormwater management and erosion control
Work schedules are subject to change depending on weather and other field conditions. For the latest, please visit: portland.gov/filtrationconstruction.
Bull Run Filtration: coffee with the contractor
The Water Bureau will host an informal drop-in session where project neighbors can chat with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There won't be a formal presentation, so drop by any time between 9 and 10:30 pm.
Date: Thursday, November 13, 2025 Time: 9-10:30 a.m. (drop in) Where: Multnomah County Grange #71, 30639 SE Bluff Road, Gresham
Can't make the event? Join us at the next Coffee with the Contractor in December.
|
|
Get construction text alerts
Sign up to receive text notifications about temporary lane closures and other construction traffic information related to the Bull Run Filtration project.
|
|
|
The Bull Run Filtration Project will remove Cryptosporidium and other contaminants from the Bull Run water supply, producing cleaner, safer water for the one million people who use our water now and for future generations. The project is required by the federal Safe Drinking Water Act and must be in operation by September 30, 2027, through a bilateral compliance agreement with the Oregon Health Authority.
To learn more, visit portland.gov/water/filtration.
|
|
|
Know someone who would be interested in updates about the Bull Run Treatment Projects? Please share the news!

The City of Portland is committed to providing meaningful access. To request translation, interpretation, modifications, accommodations, or other auxiliary aids or services, or to file a complaint of discrimination, contact 503-823-4000 (311), Relay Service & TTY: 711
Traducción e Interpretación | Biên Dịch và Thông Dịch | अनुवादन तथा व्याख्या 口笔译服务 | Устный и письменный перевод | Turjumaad iyo Fasiraad Письмовий і усний переклад | Traducere și interpretariat | Chiaku me Awewen Kapas Translation and Interpretation: 503-823-4000 (311), Relay: 711
This email was sent from an unmonitored inbox. Please do not reply. Instead, contact us at bullrunprojects@portlandoregon.gov.
|
|
|
|