Environmental Services is constructing a project that will install and upsize public sewer pipes and construct green street planters in the Buckman and Kerns neighborhoods. These improvements will increase sewer capacity, relieve sewer backups, and help reduce street flooding.
General Schedule
Construction is ongoing and is anticipated to be finished by early 2026. Work occurs in stages, and not all at once.
ADA Ramps Removed from Project Contract
Due to unforeseen design challenges and contract schedules, approximately forty two (42) ADA ramps will be removed from this project. Environmental Services will work with PBOT Maintenance to build the ADA ramps in the future. The following is a list of ramps that are removed from this contract. There is not a schedule for these yet:
- SE 20th Ave and SE Salmon St (SW corner).
- SE 22nd Ave and SE Salmon St (mid-block).
- SE 25th Ave and SE Taylor St (SE corner).
- SE 27th Ave and SE Taylor St (SW corner).
- SE 16th Ave and SE Morrison St (NW and SW corners).
- SE 15th Ave and SE Alder St (NE and SE corners).
- SE 18th Ave and SE Alder St (NW corner).
- SE 16th Ave and SE Washington St (NE corner).
- SE 17th Ave and SE Washington St (NE corner).
- SE 17th Ave and SE Stark St (SW corner).
- SE Pine St and SE 26th Ave (SW and SE corners).
- SE Pine St and SE 27th Ave (SW, SE, and NE corners).
- SE Pine St and SE 28th Ave (NE and SE corners).
- SE Pine St and SE 29th Ave (NE corner).
- SE Pine St and SE 31st Ave (SW corner).
- SE Ankeny St and SE 22nd Ave (SW, NW, and NE corners).
- SE Ankeny St and SE 27th Ave (SW and mid-block on the north side).
- SE Ankeny St and SE 28th Ave (NE corner).
- SE Ankeny St and SE 30th Ave (NE and SE corners).
- SE Ankeny St and SE 30th Pl (NE and SE corners).
- NE Couch St and NE 28th Ave (all four corners).
- NE Couch St and NE 29th Ave (NE and SE corners).
- NE Couch St and NE 30th Pl (NE corner).
- NE Couch St and NE 31st Ave (NE and SE corners).
- NE Davis St and NE 30th Ave (NW corner).
- NE Davis St and NE 32nd Ave (SW corner).
What’s Happening Now
All work is weather-dependent and subject to change.
Remainder of this week:
Construction will resume during work hours between 7:00am and 6:00pm, Monday through Friday. Work may be done on some Saturdays, as well at the following locations:
- Finish construction of sewer mainline and connections on SE Ankeny St between SE 27th and 28th avenues.
- Construct sewer connections on SE Ankeny St between SE 26th and 27th avenues.
- Start sewer connections on SE Ankeny St west of SE 26th Ave
-
Traffic Alert: East Burnside St east of SE 30th Place has one lane closed due to construction impacts and lane requirements. This spot is down to one lane for a few weeks.
- Pave at the following locations (weather dependent):
- SE Taylor St east of SE 26th Ave.
Continue work on ADA ramps and green street construction at the following locations:
- SE 17th Ave and SE Stark St.
- SE Alder St and SE 18th Ave (east of 18th).
- SE 16th Ave and SE Belmont St.
- SE Belmont St and SE 17th Ave.
- SE 20th Ave south of SE Belmont St.
- SE Ash St east of SE 28th Ave.
- NE 29th Ave south of SE Everett St.
- NE Everett St. east of NE 29th Ave.
- SE 20th Ave and SE Belmont St (SW Corner).
- SE 16th Ave and SE Belmont St (NW Corner).
- SE 30th Pl south of east Burnside St.
Week of March 3:
Construction will resume during work hours between 7:00am and 6:00pm, Monday through Friday. Work may be done on some Saturdays, as well at the following locations:
- Finish sewer connections on SE Ankeny St west of SE 26th Ave.
- Construct sewer connections on SE Ankeny St east of SE 24th Ave.
- Start construction of sewer mainline and sewer connections on SE 26th Ave between SE Ankeny and E Burnside streets.
- Pave at the following locations (weather dependent):
- SE 15th Ave north of SE Main and SE Salmon streets.
- SE 18th Ave north of SE Main St.
- SE 16th Ave and SE Washington St.
- SE Alder St at SE 16th Ave.
- SE 25th Ave south of SE Yamhill St.
- SE Taylor St east of SE 23rd Ave.
- SE 23rd Ave north of SE Salmon St.
Continue work on ADA ramps and green street construction at the following locations:
- SE 17th Ave and SE Stark St.
- SE Alder St and SE 18th Ave (east of 18th).
- SE 16th Ave and SE Belmont St.
- SE Belmont St and SE 17th Ave.
- SE 20th Ave south of SE Belmont St.
- SE Ash St east of SE 28th Ave.
- NE 29th Ave south of SE Everett St.
- NE Everett St. east of NE 29th Ave.
- SE 20th Ave and SE Belmont St (SW Corner).
- SE 16th Ave and SE Belmont St (NW Corner).
- SE 30th Pl south of east Burnside St.
Week of March 10:
Construction will resume during work hours between 7:00am and 6:00pm, Monday through Friday. Work may be done on some Saturdays, as well at the following locations:
- Continue construction of sewer mainline and sewer connections on SE 26th Ave between SE Ankeny and E Burnside streets.
Continue work on ADA ramps and green street construction at the following locations:
- SE 17th Ave and SE Stark St.
- SE Alder St and SE 18th Ave (east of 18th).
- SE 16th Ave and SE Belmont St.
- SE Belmont St and SE 17th Ave.
- SE 20th Ave south of SE Belmont St.
- SE Ash St east of SE 28th Ave.
- NE 29th Ave south of SE Everett St.
- NE Everett St. east of NE 29th Ave.
- SE 20th Ave and SE Belmont St (SW Corner).
- SE 16th Ave and SE Belmont St (NW Corner).
- SE 30th Pl south of east Burnside St.
Green street planters are built in phases with periods of inactivity between each phase. Excavation will happen first, then the contractor will build forms and pour concrete. Once the concrete has set, crews will return to fill the planters with soil. Plants and trees will be installed later when weather conditions are appropriate to plant. Please note: The holes that will be excavated for each green street planter will look bigger than the finished product.
|