ODOT Region 4 Weekly Construction Report
Oregon Department of Transportation sent this bulletin at 04/04/2014 12:28 PM PDTCentral Oregon Road Construction
UPDATE: Week of April 7, 2014
For further information contact:
Peter Murphy
541-388-6224
The Oregon Department of Transportation (ODOT) is continuing to invest in Oregon’s future with roadway improvement projects throughout Oregon’s central region (ODOT Region 4). ODOT is committed to providing safe, efficient transportations systems. The following projects reflect ODOT’s commitment to make improvements as traffic numbers rise and to make the roadways safer and more efficient for drivers:
All work is dependent on weather conditions.
DESCHUTES COUNTY
US97/ Wickiup - Bowery Lane
Repaving (grind /inlay 2") on US97 from Redmond to Bend. Concrete median island will be constructed near Yew Avenue and bridge work on Yew Avenue bridge.
Installation of Temporary Signs and Traffic Control Devices along shoulders and survey work. No lane closures or delays expected. Night work to start Sunday night, April 13. Nights 7 PM - 7AM, Sunday through Friday mornings.
US97/Murphy Road Project (Bend)
On US97 between Pinebrook and the 3rd Street/Business 97 exit, there will bridge construction in the median and shoulders during the daytime.
Road and utility work on 3rd Street south of Murphy Road. Road work on Murphy
Road from Parrell Road to 3rd Street.
Business Access remains open for all businesses on 3rd Street.
http://www.oregon.gov/ODOT/HWY/REGION4/pages/us97-murphyrd/us97-murphyrd.aspx
US20: Cascade Improvements (Sisters)
US20 is under full reconstruction in downtown Sisters between Pine Street and Larch Street with two separate detours for vehicles.
Passenger vehicles detour on Main and Hood Avenues and freight truck vehicles detour on
Barclay Drive and Locust Street.
Pedestrian access is open to businesses located within the reconstruction section.
Traffic control changes including a temporary signal and stop sign changes.
The reconstruction section of highway is anticipated to be reopened in mid-May.
US20 @ Barclay Temporary Signal (Sisters)
The temporary signal at US20 and Barclay intersection operational.
Sunriver to Lava Butte Multi-Use Path Project
Clearing and earthwork construction along all sections of the new trail. Workers will be present on USFS Roads 9702 (Benham Falls Rd), 600, 650, and 655.
JEFFERSON COUNTY
US97/ L St-Fairgrounds Rd (Madras)
Construction of curb, sidewalk, drainage facilities, lighting, landscaping, and pedestrian refuge.
Sawcutting and excavation on southbound shoulder; all lanes and business accesses are open.
KLAMATH COUNTY
OR-39:Merrill NCL -California State Line
The 5.4 mile section of OR 39 between Merrill and the California State Line will be repaved. Once paved, durable striping and centerline rumble strips will be installed on the highway segments outside of Merrill. Crosswalks in Merrill will be restriped using continental markings. Guardrails and signs in the area will be upgraded as needed.
The $2.9 million paving contract was awarded to Rocky Mountain Construction in February.
Survey work, earthwork, pipe work, and sidewalk repairs.
Minor delays possible.
OR 39: 6th St. - Merrill/Lakeview JCT
Corrective work for Signals scheduled to start 4/07/2014
Traffic controlled by flaggers during signal outages. Expect minor delays
SHERMAN COUNTY
I-84 @ US97 INTERCHANGE – BIGGS JUNCTION
MP 104.5 and MP 0 to 2
KERR Contractors is building a modernization project at the Biggs Junction Interchange. The project will significantly widen US97 and all of the interchange ramps. The project also includes new retaining walls, bridges and signals. The work will take place in stages to minimize any traffic delays. The first stage will take place this summer, and it will include constructing the West half of the new US97 bridges over I-84 and UPRR. The project will be completed in the summer of 2015.
During the week of April 6th to April 12th the contractor will continue to form the decks for the new US97 bridges over I84 and UPRR, embankment and utility work will be ongoing, and slope excavation along US97 will continue. I84 is reduced to one lane in both EB and WB direction. Speeds on I84 through the work zone have been reduced to 50 MPH. Expect occasional flagging on US97 at the ramp and US30 intersection locations for select operations. Delays during flagging operations will be less than 20 minutes. As roadway work continues to progress toward shifting traffic into stage II configuration expect to see changing traffic patterns and reduced roadway widths on US97, I-84 EB Exit, and I-84 WB On-Ramp.
WASCO COUNTY
(I-84 MOSIER WB BRIDGE STRENGTHENING) MP 69.65
ODOT has contracted with M.J. Hughes to strengthen the Mosier I-84 WB Connection Structure (Overpass to I-84). This bridge currently has a load restriction; the project will strengthen the structure to allow removal of the load restriction. The project includes installation of titanium reinforcement bar on the undersides of the bridge girders, installation of shear dowels, and an asphalt overlay. The project will be completed by June 6th.
Access to the structure will primarily be from I-84. During construction I-84 will have one lane closures both EB and WB. These closures will happen both during the day and at night. During periods of high traffic volumes motorists may experience minor delays and slow moving traffic.
During the week of April 6th to April 12th the contractor will continue injecting the girder shear cracks with epoxy. The contractor will also begin making saw cuts into the girders to allow for installation of titanium reinforcement bars.
.
####