Trucking Advisory: Ramp closure dates extended for OR 126 in Springfield
Oregon Department of Transportation sent this bulletin at 10/18/2013 12:33 PM PDT
October 18, 2013 13-209T
For more information: (503) 373-0000, option 1 for information about over-dimension loads, and (503) 378-6699 for information about registration services
Trucking Advisory: Overnight ramp closures extended again for OR 126 interchanges in Springfield
SPRINGFIELD— A paving project to resurface OR 126 (Officer Chris Kilcullen Memorial Highway) in Springfield will result in overnight ramp closures until November 1, 2013 at 42nd Street, Pioneer Parkway, and Mohawk Blvd. The work is weather dependent.
Mohawk Blvd. ramps
Effective immediately and continuing until November 1, 2013 the eastbound on- and off-ramps of OR 126 at Mohawk Blvd. will be closed intermittently between 7 p.m. and 8 a.m.
Westbound ramps will be closed intermittently between 6 p.m. and 5:30 a.m.
These closures are not on the OR 126 mainline.
Detour:
During the closure, traffic will be directed to use the 42nd St. interchange, to Marcola road, to access Mohawk Blvd.
42nd Street ramps
Effective immediately and continuing until November 1, 2013, the eastbound on-and-off-ramps of OR 126 at 42nd Street will be closed intermittently between 7 p.m. and 11 a.m.
Westbound ramps will be closed intermittently between 6 p.m. and 5:30 a.m.
These closures are not on the OR 126 mainline.
Detour:
During the closure, traffic will be directed to use the Mohawk Blvd. interchange, approximately one mile west of 42nd Street, to access Marcola Road and 42nd Street.
OR 126 eastbound and westbound on and off ramps to and from Pioneer Parkway (OR 528) & “Q” Street (Springfield)
Effective immediately and continuing until November 1, 2013 the on and off ramps to and from OR 126 eastbound and westbound to Pioneer Parkway (OR 528) and “Q” Street will be closed intermittently between 7 p.m. and 8 a.m.
Detour:
During the ramp closures, legal size freight traffic will be directed to Mohawk Blvd. (one mile east of Pioneer Parkway exit), to Centennial Blvd., to Pioneer Parkway.
Entire project to be completed in October
The OR 126: Springfield Paving and Cable Median Barrier project will preserve the existing highway by grinding and replacing two inches of asphalt in most areas and reconstructing the eastbound portions of the 42nd Street interchange. The project will also improve safety by constructing cable median barrier between Mohawk Blvd. and East Main Street (MP 6.24-9.97).
The project is scheduled for completion by November 1, 2013
Road restriction/dates may change due to weather or other unforeseen delays; you may view the latest restriction list at:
http://www.oregontruckingonline.com/cf/MCAD/pubMetaEntry/restrictionsList/