How do you move a 1,030-foot bridge sideways? Slowly.
 Over the weekend, engineers slid the 1,030-foot, 18 million-pound northbound side of the Abernethy Bridge outward to create space in the center of the bridge for a future lane.
Watch the time-lapse video of this unusual engineering feat
News media contact: David House, 503-551-8641
Nov. 23, 2026
You wouldn't notice it happening if you were watching in person. But over the weekend, a 1,030-foot section of the Abernethy Bridge on Interstate 205 moved almost eight feet sideways.
The move is part of a unique approach to widening the interstate bridge over the Willamette River between Oregon City and West Linn. Crews are sliding its two sides apart to make room for 16 additional feet in the middle for future construction.
Moving a bridge isn't as simple as pushing it sideways. Especially when the section being moved is over 1,000 feet long and weighs about 9,060 tons – or 18,120,000 pounds.
First, crews use powerful hydraulic jacks to lift the bridge structure about two inches off its supports. Then another set of hydraulic jacks pushes it sideways, slowly and carefully, about four inches every 15 minutes.
"We picked it up about two inches, and then we moved it over about seven and a half feet, and then we put it back down on its supports," project Resident Engineer Ian Cannon said.
At that pace, the slide took about six hours starting late Friday night into early Saturday morning. Crews worked around the clock over the weekend to move the northbound side of the bridge onto newly widened, earthquake-resilient piers.
After the slide, crews inspected the structure, reconnected the bridge to the roadways at each end, restored lighting connections and guardrail, and restriped the lanes before reopening the bridge to traffic.
"We moved it an inch at a time to make sure we were keeping it straight and not over-stressing the bridge, and once we got it where we wanted it, we lowered it down again," Cannon said. "The lifting and moving of a very large bridge is very unusual just because of the magnitude of it."
Drivers will notice that the lanes have shifted, but crossing the bridge will feel much the same as before.
The southbound side will get its turn during another weekend later this year, moving about eight feet in the opposite direction.
When both slides are complete, the two sides of the bridge will be 16 feet farther apart, making room for additional space for construction in the future.
The bridge slide is just one part of a major project that will result in the first interstate highway bridge over the Willamette River in the Portland-metro area that is able to withstand a major earthquake. The project includes widening the bridge – including the weekend slides – realigning nearby on- and off-ramps, and building new bicycle and pedestrian routes.
Bridge construction is expected to finish sometime in 2027.