NEWS RELEASE:
Second Arizona Landslide emergency repair project completed on schedule
 Contractors for ODOT completed work on a 200-foot-deep shaft at the south end of the Arizona Inn Landslide area earlier this month. The shaft will act as a giant catch basin for a new drainage system that was installed along the hillside east of U.S. Highway 101. The top of the shaft can be seen behind the guardrail in this Nov. 2 photo.
A new drainage system will stabilize the hillside above U.S. 101 and help keep the highway open near Port Orford
Nov. 23, 2026
PORT ORFORD – Contractors for the Oregon Department of Transportation finished work earlier this month on the second of three permanent emergency repair projects that will help keep U.S. Highway 101 open along the southern Oregon coast.
The Arizona Inn Landslide area, located near the Arizona Beach Recreation Area about 10 miles south of Port Orford, has been the scene of several landslides over the past century. The most recent closed the highway for four days in January 2023.
In response, ODOT developed a plan to stabilize the area by installing a vast drainage system along the Arizona Inn hillside. A similar system built in the 1990s had been damaged by ground movement.
The plan to stabilize the slope consisted of two projects or phases. The first installed more than 65,000 feet of drainage pipes along the hillside and was completed in 2024. The second involved building a 200-foot-deep collector shaft that would act as a giant catch basin for the new drainage system.
ODOT worked with Delve Underground, a consultant specializing in transportation and tunnels, to design a shaft about 100 feet south of the landslide area, where it would be less vulnerable to ground movement.
Following a competitive bid process, Portland-based Condon-Johnson & Associates, Inc., was awarded the $18.3 million contract to build the shaft.
Excavation began in April 2025 and the shaft was mostly completed 10 months later. Through the spring and summer of 2026, Condon-Johnson connected the array of drainage pipes to the new shaft.
Several work items related to the old shaft were added to the original contract, pushing back the scheduled completion by two months to Nov. 25. Condon-Johnson completed all work on Nov. 12.
Final work next year
With the completion of the new drainage system, ODOT will move to the third and final phase next year.
Phase 3 will widen the roadway and rebuild the northbound passing lane. The $3.5 million project is scheduled to bid in February and construction will likely continue through summer. This work will require lane closures with flaggers.
The passing lane has been closed since the 2023 landslide.
For more information, visit the project webpage or contact ODOT Public Information Officer Dan Latham at 541-817-5200 or Dan.Latham@odot.oregon.gov.
## ODOT ##
[MEDIA NOTE: Additional photos are available on the project webpage and Flickr page.]
 About six feet of water has collected at the bottom of the Arizona Landslide shaft and several arrays of drainage pipes can be seen along the wall in this Sept. 22 photo. A total of 125 two-inch drainage pipes are connected to the shaft, which is 200 feet deep. The shaft will act as a giant catch basin for a new drainage system that was installed throughout the Arizona Inn Landslide area.
|