This weekend, all lanes of northbound I-205 across the Abernethy Bridge will close to allow crews to 'slide' the northbound side of the bridge by about eight feet onto newly widened support piers. The closure begins this Friday, Nov. 20 at 10 p.m. and ends on Monday, Nov. 23 by 5 a.m.
 Two of several hydraulic jacks currently positioned under the Abernethy Bridge ready to lift up and slide over the northbound direction about eight feet.
Closure details
- Weekend closure of northbound I-205 across the Abernethy Bridge (between OR 43 and OR 99E) starting this Friday, Nov. 20 at 10 p.m. to Monday, Nov. 23 at 5 a.m.
- The following I-205 northbound ramps will also close this weekend:
- Stafford Road on-ramp.
- 10th Street on-ramp.
- OR 43 on-ramp.
- All northbound I-205 traffic will be required to exit at the OR 43 off-ramp.
Local and Regional Detours
- Northbound traffic will bypass I-205 in this section by using detours on I-5 and I-84.
- Local traffic can use the Arch Bridge to cross the river.
- Southbound I-205 lanes will remain open.
Drivers should plan ahead, follow posted detour signs and allow extra travel time. Crews will be working 24/7 during the closure. Neighbors should expect construction activity and some daytime and nighttime noise throughout the weekend. Work could be postponed with strong winds in the forecast.
A second weekend closure will take place a few weeks later on southbound I-205 while crews slide that side of the bridge. We will share confirmed dates and additional details before that work begins. The closure will not take place on a major holiday weekend.
Visit the project website for details including additional traffic impacts in the area.
 Abernethy Bridge regional detour using I-5 and I-84 during this weekend's closure of northbound I-205. Stafford Road, 10th Street and OR 43 on-ramps to northbound I-205 will also close for the weekend.
 Abernethy Bridge local detour using the Arch Bridge during this weekend's closure of northbound I-205.
The 'bridge slide' is the method we are using to widen the main portion of the I-205 Abernethy Bridge over the Willamette River. Over the course of two separate weekends, crews will ‘slide’ the northbound and southbound sides of the Abernethy Bridge apart onto newly widened support piers, creating space for an additional 16 feet of roadway in the middle.
To move each side, crews will first use hydraulic jacks to lift the upper bridge structure about two inches off its existing bridge supports. Additional hydraulic jacks will then push the bridge sideways at a carefully controlled pace of about four inches every 15 minutes. Each side will move about eight feet. After each slide, crews will complete a thorough inspection, reconnect the joints between the bridge and the approaches, reconnect lighting and restripe the lanes before reopening to traffic. Drivers will notice a shift in traffic lanes when the bridge reopens, but the overall driving experience will stay largely the same.
When evaluating options for building a wider bridge, we chose the bridge slide method because it not only distributes the weight of the new bridge deck evenly, it also costs less and is less disruptive than building a new bridge.
What is this project?
ODOT is upgrading the Abernethy Bridge, which spans the Willamette River between Oregon City and West Linn, to withstand a major earthquake. We are also widening the bridge and improving safety by realigning on- and off-ramps near the bridge and building new bicycle and pedestrian routes. The bridge work is expected to finish in 2027.
|