I-205 Abernethy Bridge Project: Reminder! This weekend's closure of northbound I-205 on the Abernethy Bridge, Nov. 20-23

Having trouble viewing this email? View it as a Web page.

I-205 Improvements, Abernethy Bridge logo

In this email:


Reminder! This weekend's closure of northbound I-205 across the Abernethy Bridge

This weekend, all lanes of northbound I-205 across the Abernethy Bridge will close to allow crews to 'slide' the northbound side of the bridge by about eight feet onto newly widened support piers. The closure begins this Friday, Nov. 20 at 10 p.m. and ends on Monday, Nov. 23 by 5 a.m.  

Photo of two hydraulic jacks under the I-205 Abernethy Bridge

Two of several hydraulic jacks currently positioned under the Abernethy Bridge ready to lift up and slide over the northbound direction about eight feet.


Closure details

  • Weekend closure of northbound I-205 across the Abernethy Bridge (between OR 43 and OR 99E) starting this Friday, Nov. 20 at 10 p.m. to Monday, Nov. 23 at 5 a.m. 
  • The following I-205 northbound ramps will also close this weekend:
    • Stafford Road on-ramp.
    • 10th Street on-ramp.
    • OR 43 on-ramp.
  • All northbound I-205 traffic will be required to exit at the OR 43 off-ramp. 

Local and Regional Detours

  • Northbound traffic will bypass I-205 in this section by using detours on I-5 and I-84.
  • Local traffic can use the Arch Bridge to cross the river.
  • Southbound I-205 lanes will remain open.

Drivers should plan ahead, follow posted detour signs and allow extra travel time. Crews will be working 24/7 during the closure. Neighbors should expect construction activity and some daytime and nighttime noise throughout the weekend. Work could be postponed with strong winds in the forecast.

A second weekend closure will take place a few weeks later on southbound I-205 while crews slide that side of the bridge. We will share confirmed dates and additional details before that work begins. The closure will not take place on a major holiday weekend.

Visit the project website for details including additional traffic impacts in the area.

Map showing that I-205 north is closed for a weekend and a detour route takes drivers onto I-5 and I-84.

Abernethy Bridge regional detour using I-5 and I-84 during this weekend's closure of northbound I-205. Stafford Road, 10th Street and OR 43 on-ramps to northbound I-205 will also close for the weekend.


Map of the Oregon City and West Linn with I-205 northbound across the Abernethy Bridge closed with a local detour onto the Arch Bridge

Abernethy Bridge local detour using the Arch Bridge during this weekend's closure of northbound I-205.


What is the 'bridge slide'?

The 'bridge slide' is the method we are using to widen the main portion of the I-205 Abernethy Bridge over the Willamette River. Over the course of two separate weekends, crews will ‘slide’ the northbound and southbound sides of the Abernethy Bridge apart onto newly widened support piers, creating space for an additional 16 feet of roadway in the middle. 

To move each side, crews will first use hydraulic jacks to lift the upper bridge structure about two inches off its existing bridge supports. Additional hydraulic jacks will then push the bridge sideways at a carefully controlled pace of about four inches every 15 minutes. Each side will move about eight feet. After each slide, crews will complete a thorough inspection, reconnect the joints between the bridge and the approaches, reconnect lighting and restripe the lanes before reopening to traffic. Drivers will notice a shift in traffic lanes when the bridge reopens, but the overall driving experience will stay largely the same.

When evaluating options for building a wider bridge, we chose the bridge slide method because it not only distributes the weight of the new bridge deck evenly, it also costs less and is less disruptive than building a new bridge. 


What is this project?

ODOT is upgrading the Abernethy Bridge, which spans the Willamette River between Oregon City and West Linn, to withstand a major earthquake. We are also widening the bridge and improving safety by realigning on- and off-ramps near the bridge and building new bicycle and pedestrian routes. The bridge work is expected to finish in 2027.  

Question or comments?


Translation/Interpretation accommodations

For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call 503-731-4128, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128.

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128.

如果您想瞭解這個項目翻譯成 繁體中文 的相關資訊,請致電 503-731-4128.

如果您想了解这个项目翻译成 简体中文 的相关信息,请致电 503-731-4128.

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: 503-731-4128.

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.


Work Zone Safety

For 24/7 road conditions and traffic alerts visit tripcheck.com or call 5-1-1.

 

Visit the Portland Area Construction Information website for more information about projects in construction.