Region 4 Weekly Construction Update

Having trouble viewing this email? View it as a Web page.

May 29, 2026 - June 5, 2026

Region 4 Weekly Construction Update


Here at ODOT, we are committed to providing a safe and efficient transportation system for everyone. We invest in Oregon's future through roadway improvement projects. The following projects are located within Region 4; Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.

There are two ways to learn about construction taking place for the upcoming week. 

1. Visit TripCheck.com. Constantly updated with construction and crash data, TripCheck is the best way to learn about road conditions around the state. Click on a traffic cone symbol on the map to see construction impacts for that area.


2. Scroll down to the counties and highways listed below to see impacts that could affect you. Construction information is shown for one week, giving you the most up-to-date information.

All work is dependent on weather conditions, and schedules are subject to change.


DESCHUTES COUNTY

Driver Feedback Signs (Deschutes County)

Crews will be installing sign footings on Alfalfa Market Road. Work will take place Monday through Friday from 7 a.m. to 5 p.m. No delays expected.

More project information here

Expected completion- Fall 2026.

 

U.S. 97 & U.S. 20 Curb Ramps (Bend/Sisters)

BEND: Crews will be performing work on U.S. 20 at the intersections of Purcell, 27th and Windy Knolls to install new ADA ramps. The work will occur Monday - Thursday from 8 p.m. - 6 a.m. Drivers can expect minimal delays.

SISTERS: No work this week.

More project information here

Expected completion- December 2026.

 

U.S. 97: Lower Bridge Way - Northwest 10th Street (Terrebonne)

Smith Rock Way is closed from U.S. 97 to 16th Street. Local traffic has access to their homes and businesses via 16th Street.

Lower Bridge Way at U.S. 97 is fully closed to traffic. There is no access to or from Lower Bridge Way at U.S. 97, but U.S. 97 will remain open in both directions​​​. Please use signed detours.

Access to 11th Street on the north end of Terrebonne is closed. Please use Central Avenue.

Access to 11th Street on the south end of Terrebonne will be limited to U.S. 97, Central Avenue and C Street.

Access to the intersection of Smith Rock Way and 11th Street will be limited, use posted detour for access.

More project information here. 

Expected completion- May 2027

 

Redmond/ Prineville ADA Ramps

REDMOND: Night work is scheduled Monday through Friday from 7:00 p.m. to 7:00 a.m. to minimize traffic impacts. Nearby residents should expect nighttime construction noise.

Crews will be performing single lane closures on Highland from 15th Street to 27th Street and, at 6th and Quince Sttreets to construct new ADA ramps and enhance signal operations. The single lane closures will be nightly Monday - Thursday from 7p.m. to 7a.m.

Crews will be performing single lane closures on U.S. 97 northbound and southbound between Highland and Evergreen, Monday through Thursday night, from 7p.m. - 6 a.m. 

Minor delays are expected.

PRINEVILLE: No work this week. 

More project information here.

Expected completion- September 2026

 

GILLIAM, SHERMAN & WASCO COUNTIES

U.S. 97 Morro - Grass Valley

Crews will be on-site periodically setting up traffic control signing and performing construction survey work outside of the travel lanes. No traffic impacts are expected this week.

More project information here.

Expected completion- October 2026

 

I-84 / U.S. 197: The Dalles, Rufus & Arlington Bridges

THE DALLES: No work expected this week.

RUFUS: Crews will be on-site performing night paving work between 8 p.m. and 6 a.m. Monday night through Friday morning. Motorists should anticipate full-time single lane closures beginning Monday and ending Friday at noon for both eastbound and westbound I-84 between mile point 107 and 110. 

ARLINGTON: Crews will be on-site performing barrier work between 8 p.m. and 6 a.m. Monday night through Friday morning. Motorists should anticipate full-time single lane closures beginning Monday and ending Friday at noon for both eastbound and westbound I-84 between mile point 137 and 139. 

Expected completion- June 2026

 

KLAMATH COUNTY

OR 39: Merrill SRTS (Safe Routes to Schools) Project 

Traffic through the work zone will be managed by flaggers, expect delays up to 20 minutes. 

North Polk Street will be closed to through traffic from OR 39 to West 1st Street. Please use detour in place.

Falvey Road will be closed to through traffic at the OR 39 intersection. Please use the detour in place.

More project information here.

Expected completion - October 2026

 


Questions or comments?

Meghan Blyth, community affairs coordinator 

541-316-3941 or Meghan.L.Blyth@odot.oregon.gov

For current road and weather conditions visit TripCheck.com or call 511

 

Accommodation or Translation Requests

To request information in an alternative format or to request an accommodation under Civil Rights Title VI, call 541-316-3941 or use the statewide Oregon Relay Service: 7-1-1.

Where traffic is routed through or around a work zone, pedestrians, including those with disabilities, will also be provided routes through or around the work zone.

To request information in other languages, call 541-316-3941.

Para solicitar información en otros idiomas, llame a 541-316-3941.