Southwest Oregon Construction Report for the week of April 5-11, 2026
The following report includes ODOT highways that are impacted by construction in Josephine, Jackson, Coos, Curry and Douglas counties. Projects are listed in the following order: highway, location, project name. Project construction costs (bid amount) are provided when the information is available.
Pedestrian routes: Where traffic is routed through or around a work zone, pedestrians, including those with disabilities, will also be provided routes through or around the work zone.
Open for business: In areas with active construction, blue cones are often used to identify an open business access or driveway.
Know before you go! Visit www.TripCheck.com for road conditions and traffic cameras or dial 5-1-1. Visit the ODOT website at www.oregon.gov/ODOT/ for more information.
COOS COUNTY
OREGON 42 (Coos Bay-Roseburg Highway), MP 0.0 - 9.7, U.S. 101 to Cedar Point Road paving, culvert and bridge repairs ($11.77 million), website
This project will pave nearly seven miles of Oregon 42, repair seven bridges and repair or replace 25 culverts between the U.S. 101 junction and Coquille. The project will also install a continuous center turn lane between Green Acres Lane and Fernwood Road (MP 3.3-7.3) and add centerline rumble strips between Fernwood Road and Cedar Point Road (MP 7.3-9.7). All work is scheduled for completion this fall.
Watch for intermittent lane closures throughout the work zone as the contractor replaces guardrail. Watch for traffic control devices and expect congestion and delays at peak travel times.
Drivers should also watch for a traffic pattern change between Green Acres Lane and Fernwood Road. The roadway has been restriped to create a center turn lane, allowing drivers to safely move out of the travel lanes to make left turns.
OREGON 42 (Coos Bay-Roseburg Highway), MP 20.8 to 21.9 (Myrtle Point), ADA curb ramp replacement project ($2,310,000), website
This project will improve pedestrian facilities by building ADA-compliant sidewalk curb ramps at approximately 31 intersections in Brookings, Gold Beach, Myrtle Point and Roseburg. All work is scheduled to be completed by July 16.
Construction in Myrtle Point involves six intersections along Oregon 42, from Bothwick Street to Carlisle Lane (MP 20.8-21.9). Watch for intermittent lane, shoulder and sidewalk closures. Construction will likely take place Monday-Friday, 7 a.m. to 4 p.m., though traffic impacts may continue 24/7 through the work zone. When sidewalks are closed, alternate pedestrian routes will be provided.
OREGON 42 (Coos Bay-Roseburg Highway), MP 36.1 Rockfall mitigation project ($495,540)
This project will improve safety at a slide area along Oregon 42 by removing loose rock from the slope next to the highway and adding a new drainage ditch. All work is scheduled to be completed by May 25.
Watch for intermittent lane closures with flaggers or automated flagging machines Monday to Friday, 7 a.m. to 5 p.m. Watch for traffic control devices and expect congestion and delays at peak travel times.
OREGON 241 (Coos River Highway), MP 3.5-3.8, Chandler (Coos River) Bridge painting and repairs ($7.29 million), website
This project will paint the steel truss section of the bridge, replace the lift-span tower ladders and access platforms, and upgrade the steel guardrail at each end of the bridge. Construction will require lane closures across the bridge and two weekend closures of the highway, to be announced when schedules are available. All work is scheduled to be completed by Sept. 18.
Highway traffic across the bridge is limited to a single lane 24/7 until September. Watch for concrete rail along the centerline of the bridge. A temporary signal will provide traffic control. Most delays will be less than 5-10 minutes.
CURRY COUNTY
U.S. 101 (Oregon Coast Highway), MP 312, Arizona Landslide repair ($18.3 million)
This project will help reduce ground movement at the Arizona Landslide Complex, located 12 miles south of Port Orford, by building a deep shaft that will act as a giant catch basin for the new drainage system. Construction is scheduled for completion in November.
Most work will take place on the west side of the highway. Drivers should watch for construction workers, equipment and vehicles along the shoulder.
U.S. 101 (Oregon Coast Highway), MP 327.4-329.5 (Gold Beach) and MP 354.8-359.3 (Brookings), ADA curb ramp replacement project ($2,310,000) website
This project will improve pedestrian facilities by building ADA-compliant sidewalk curb ramps at approximately 31 intersections in Brookings, Gold Beach, Myrtle Point and Roseburg. All work is scheduled to be completed by July 16.
Construction involves eight intersections in Gold Beach (U.S. 101 from Wedderburn Loop Road to Kerber Drive, MP 327.4-329.5) and 12 in Brookings (U.S. 101 from Dawson Road/OR 255 to Benham Lane, MP 354.8-359.3).
In both communities, watch for intermittent lane, shoulder and sidewalk closures. Construction will likely take place Monday-Friday, 7 a.m. to 4 p.m., though traffic impacts may continue 24/7 through the work zone. When sidewalks are closed, alternate pedestrian routes will be provided.
DOUGLAS COUNTY
INTERSTATE 5 (Pacific Highway), MP 1-163, Southern Oregon Wrong Way Driver Mitigation project ($2.5 million), website
This project improves safety along Interstate 5 by adding features that alert drivers when they enter an interchange off-ramp from the wrong direction. These enhancements include permanent signs, reflective pavement markings and flashing beacons. The project will involve most off-ramps on I-5 from the California border to the Curtin interchange (MP 1-163).
During April, the contractor will install signs along I-5 interchange off-ramps in Douglas County. About 40 off-ramps may be closed for a few hours at night while work is taking place. Only one ramp will be closed at any given time, and only for about 2-4 hours. During ramp closures, drivers are advised to watch for message boards, and use alternate routes, such as driving to the next interchange and turning around. Drivers should also watch for construction vehicles and workers along off-ramp shoulders.
OREGON 38 (Umpqua Highway), MP 4.9, Hinsdale Slough culvert ($322,522)
This project will build a retaining wall along the south side of the highway to extend the life of the culvert. Most construction has been completed.
Watch for daytime lane closures with flaggers through the work zone as the contractor cleans up and moves out. Expect delays up to 20 minutes.
OREGON 42 (Coos Bay-Roseburg Highway), MP 72-77 (Winston and Green District), Lookingglass Creek to I-5 paving and safety improvements ($11.97 million), website
This project will resurface a five-mile section of Oregon 42 between Winston and Interstate 5, install a new traffic signal at Rolling Hills Road, add safety features to help reduce crashes through the Green District, and upgrade sidewalk curb ramps to better accommodate wheelchair users and other pedestrians. The project is scheduled for completion in September.
For the weeks of April 5-11, April 12-18 and April 19-25, nighttime road construction is planned in Winston for the section of Oregon 42 (Douglas Blvd. and NW Main St.) that extends from Lookingglass Creek through the Cheetah intersection to Lookingglass Road. Some additional work may take place in the Green area of Oregon 42. Watch for intermittent lane closures through these areas 7 p.m. to 7 a.m. each Sunday night to Friday morning. Flaggers will provide traffic control as needed. Watch for construction signs and construction vehicles. Contractors are working on utility adjustments, pavement repairs, and paving side road approaches. Nearby residents should expect nighttime noise consistent with road construction.
From April 26 to May 13, watch for intermittent weeknight (6 p.m. to 6 a.m., Sunday night to Friday morning) northbound and southbound ramp closures at I-5 Exit 119, which connects with Oregon 42 and Winston. Drivers are advised to watch for message boards and use alternate routes.
OREGON 138E (North Umpqua Highway), MP 0.5-1.4 (Roseburg), ADA curb ramp replacement project ($2,310,000) website
This project will improve pedestrian facilities by building ADA-compliant sidewalk curb ramps at approximately 149 locations in Brookings, Gold Beach, Myrtle Point and Roseburg. All work is scheduled to be completed by July 16.
Construction in Roseburg will be located along OR 138E (North Umpqua Highway / Diamond Lake Blvd.) between Fulton Street and Miguel Street. Watch for intermittent lane, shoulder and sidewalk closures. Construction will likely take place Monday-Friday, 7 a.m. to 4 p.m., though traffic impacts may continue 24/7 through work zones. When sidewalks are closed, alternate pedestrian routes will be provided.
JACKSON COUNTY
INTERSTATE 5 (Pacific Highway), MP 1-163, Southern Oregon Wrong Way Driver Mitigation project ($2.5 million), website
This project improves safety along Interstate 5 by adding features that alert drivers when they enter an interchange off-ramp from the wrong direction. These enhancements include permanent signs, reflective pavement markings and flashing beacons. The project will involve most off-ramps on I-5 from the California border to the Curtin interchange (MP 1-163).
Watch for construction vehicles and workers along off-ramp shoulders as the contractor completes work on the ramps in Jackson and Josephine counties.
For the week of April 6-10, watch for intermittent closures of the southbound off-ramp at Exit48 (Rogue River) at night. Watch for message boards and use alternate routes.
OREGON 99 (Rogue Valley Highway), MP 10.2 to 11, Glenwood to Coleman Creek utility work ($12 million) website
This project will widen Oregon 99 from East Glenwood Road to Coleman Creek Bridge, improving safety, as well as pedestrian and bicycle accessibility. Other improvements include adding streetlights at four intersections, a new drainage system, and several mid-block pedestrian crossings with flashing beacons.
Watch for intermittent lane closures on OR 99 through the work zone, Monday through Friday.
VARIOUS HIGHWAYS, Jackson County Curb Ramps, Phase 2 ($11.9 million), website
This project will bring 113 pedestrian curb ramps located in Jackson County into compliance with the Americans with Disabilities Act. The ramps are mostly located along state highways in Central Point, White City, Medford, Talent and Ashland. See project website for specific locations. All work is scheduled for completion this fall.
In general, construction will require intermittent lane and shoulder closures. When sidewalks are closed for construction, alternate pedestrian routes will be provided.
JOSEPHINE COUNTY
INTERSTATE 5 (Pacific Highway), MP 1-163, Southern Oregon Wrong Way Driver Mitigation project ($2.5 million), website
This project improves safety along Interstate 5 by adding features that alert drivers when they enter an interchange off-ramp from the wrong direction. These enhancements include permanent signs, reflective pavement markings and flashing beacons. The project will involve most off-ramps on I-5 from the California border to the Curtin interchange (MP 1-163).
Watch for construction vehicles and workers along off-ramp shoulders as the contractor completes work on the ramps in Jackson and Josephine counties.
INTERSTATE 5 (Pacific Highway), MP 58.1-66.7, Monument Drive to north Grants Pass ($25 million), website
This project area, located north of Grants Pass, involves 10 miles of I-5 and ramps at four interchanges. The project will repair pavement along the I-5 travel lanes and ramps, replace bridge joints, remove roadside hazards and install guardrail. Construction is scheduled for completion this fall.
For the week of April 5-10, Sunday morning to Friday afternoon, watch for intermittent I-5 lane closures through the work zone for shoulder work and guardrail installation. Watch for construction signs and traffic control devices.
For the week of April 12-17, Sunday night to Friday morning, watch for nighttime work, to include intermittent I-5 lane closures through the work zone for shoulder work and guardrail installation. Watch for construction signs and traffic control devices.
For the week of April 26 to May 1, Sunday evening to Friday morning, the southbound I-5 Exit 61 on-ramp from Monument Drive will be closed at night, 7 p.m. to 7 a.m. Drivers are advised to use alternate routes.
For the week of May 17-22, Sunday evening to Friday morning, the southbound I-5 off-ramp at Exit 58 (North Grants Pass) is scheduled to be closed at night (7 p.m. to 7 a.m.), weather permitting. Drivers are advised to use alternate routes.
Watch for intermittent I-5 lane closures through the work zone for shoulder work and guardrail installation. Watch for construction signs and traffic control devices. Flaggers will provide traffic control on the ramps as needed. The rest areas will remain open during this work phase.
Due to heavy fog and limited visibility, drivers are asked to use headlights through the work zone.
For more information:
ODOT projects in Coos, Curry and Douglas counties: Dan Latham, Public Information Officer, 541-817-5200 or Dan.Latham@odot.oregon.gov
ODOT projects in Josephine and Jackson counties: Mary Dillinger, Public Affairs/Community Affairs Specialist, 541-621-3074 or Mary.Dillinger@odot.oregon.gov
## ODOT ##
|