This section of OR 217 will close for the weekend of June 27-30 for the third of five weekends of final paving in the Auxiliary Lanes Project. This closure was rescheduled due to last weekend’s rain.
Southbound OR 217 to close from SW Canyon Road to OR 99W weekend No. 3 of paving
News media contact: David House, 503-551-8641.
This closure for final paving was rescheduled due to last weekend’s rain
June 23, 2025
The third weekend directional closure of southbound OR 217 from Canyon Road to OR 99W is scheduled to begin at 9 p.m. Friday, June 27, and end by 5 a.m. Monday, June 30.
This closure was rescheduled due to rain last weekend. The section that will close this weekend will be the same southbound project area as the first two weekend closures earlier in June.
Paving and striping are dependent on weather and equipment availability, which means details may change. Please check the project website and your inbox regularly for the most up-to-date project information and Tripcheck.com for current travel and closure information.
For the rest of this week, drivers should continue to expect to travel temporarily on rougher, ground-down surface on parts of OR 217 south between Greenburg Road and OR 99W. There are abrupt pavement edges along the shoulder in some locations, so please continue to drive with caution.
The new auxiliary lanes may not open right away – crews might still need to use them to finish work along the shoulders and side slopes.
Final paving will require two more weekend closures later this summer, but they have not been scheduled yet. At least one of those weekends will pave the project section on the northbound side of 217. We will not close both northbound and southbound at the same time.
The overall project remains on schedule to be completed by the end of this year.
This weekend’s closure details:
All southbound lanes of OR 217 will close for the weekend from Canyon Road to OR 99W. Southbound drivers will exit OR 217 at Canyon Road, and these southbound ramps will close for the weekend:
- Beaverton-Hillsdale Highway on-ramp.
- Allen Boulevard off-ramp.
- Denney Road on-ramp.
- Hall Boulevard off-ramp.
- Hall Boulevard on-ramp.
- Scholls Ferry Road off-ramp.
- Scholls Ferry Road on-ramp.
- Greenburg Road off-ramp.
- Greenburg Road on-ramp.
- OR 99W off-ramp.
The recommended detour is to use eastbound U.S. 26 and southbound I-405 to I-5. Check Tripcheck before you hit the road this weekend.
Background
The OR 217 Auxiliary Lanes project will improve safety and reduce bottlenecks on the highway by adding auxiliary lanes, or ramp-to-ramp connections, between Beaverton-Hillsdale Highway and OR 99W. We are also making targeted improvements to local bicycle and pedestrian routes.
Work began in 2021 and is on pace to finish on time by the end of 2025. The $174 million project is funded mostly by House Bill 2017. The City of Beaverton and Washington County also contributed money toward the project.
|