I-205 Abernethy Bridge Project Updates and Traffic Impacts

Having trouble viewing this email? View it as a Web page.

Project Update

I-205 Abernethy Bridge Project Updates


Project Traffic Impacts

As work activity increases, there are multiple lane reductions, ramp closures and signed detours occurring throughout the project area. Current and complete details and detour maps can be found on the project website.

May 2-9 Traffic Impacts

  • I-205
    • May 5-7 - Nighttime partial ramp closure from I-205 southbound to OR43 northbound 8 pm to 6 am Monday through Wednesday.

      • Right lane closure

      • OR43 northbound traffic detour via roundabout 

  • OR 99E
    • May 2 - Overnight lane closures on OR 99E northbound from 10 p.m. to 5 a.m. One lane will remain open.
    • May 2-9 - Overnight ramp closure from OR 99E to I-205 northbound from 10 p.m. to 5 a.m.
    • Pedestrian detours on OR 99E.
  • OR 43
    • May 2-9 – Lane closures at I-205.
    • May 5-7 - Overnight lane closures on OR 43 northbound from 8 p.m. to 6 a.m. Monday to Wednesday.
    • May 8-9 - Overnight lane closures on OR 43 southbound from 8 p.m. to 6 a.m. Thursday to Friday.
    • Pedestrian detours on OR 43.
  • Local roads
    • May 5-9 - Daytime flagging on Clackamette Drive from 8 p.m. to 5 a.m. Monday through Friday.

The latest information on traffic impacts will be available at TripCheck.com.

As with any construction project, closure dates and timing are subject to change.


Future Work - Piledriving for bridge foundation work

Coming this summer, May-June 2025 (tentative)

Entering Spring, most of the foundation work needed to make the bridge able withstand a major earthquake is complete. One of the final pieces of foundation work is set to begin in mid-May and could last four weeks. This portion of the project will require piledriving at the base of the bridge on the Oregon City side during daylight hours.

More details will be provided before construction begins. 


Abernethy Bridge deck demolition night work

Demolition work continues on the I-205 Abernethy Bridge decks.


Bridge deck demolition continues

Overnight deck demolition work to remove portions of the existing bridge deck in preparation for the eventual widening of the structure continued this week. After pausing for the weekend, work will resume Monday, May 5 through Friday, May 9.  

Demolition work will continue through May. Work will happen from 9:30 p.m. until 4:30 a.m. each night. Some work will occur during the daytime, when it can be done safely.

Follow the progress live on the project construction cameras.

We know the noise from construction work can be disruptive. We appreciate your patience.

Residents in the vicinity of the construction area should anticipate elevated noise levels while this work is occurring. A 24/7 nighttime noise hotline is available at: 503-276-7809.


Waterline installation along OR 43 continues

Rock excavation work continues under the Abernethy Bridge on the West Linn side adjacent to OR 43. This work focuses on excavating channels through solid basalt to accommodate waterline installation. 

The majority of the work will happen between 7 a.m. and 8 p.m. Monday through Friday. There is a chance overnight excavation work may be necessary.


Sign up for updates

Don't keep this a secret – help us spread the word!

Share this email with your friends, family and neighbors so they can also get connected and sign up to receive email and text updates to learn about the work we're doing.


What is this project?

ODOT is upgrading the Abernethy Bridge, which spans the Willamette River between Oregon City and West Linn, to withstand a major earthquake. Additional improvements are being made to the bridge's adjacent on- and off-ramps to improve safety. This work is expected to be completed in 2026.  


Work Zone Safety

Questions or comments?

Ryan McCrary, ODOT Community Affairs

Ryan.MCCRARY@odot.oregon.gov
503-983-5506

For more information, visit www.i205corridor.org 

 


Translation/Interpretation Accommodations

For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call 503-731-4128, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.

 

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128.

 

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128.

 

如果您想瞭解這個項目翻譯成 繁體中文 的相關資訊,請致電 503-731-4128.

 

如果您想了解这个项目翻译成 简体中文 的相关信息,请致电 503-731-4128.

 

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: 503-731-4128.

 

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.

 


For 24/7 road conditions and traffic alerts visit tripcheck.com or call 5-1-1.

 

Visit the Portland Area Construction Information website for more information about projects in construction.