I-205 Abernethy Bridge Project Updates and Traffic Impacts

Having trouble viewing this email? View it as a Web page.

Project Update

I-205 Abernethy Bridge Project: Deck demolition and waterline installation continues


Girder removed from NB span

Demolition work allowed this girder to be removed from the I-205 Abernethy Bridge northbound deck.


Bridge deck demolition continues

OREGON CITY – Overnight deck demolition work to remove portions of the existing bridge deck in preparation for the eventual widening of the structure continued this week. After pausing for the weekend, work will resume Monday, April 28 through Friday, May 2 as progress continues.  

Demolition work will continue through May. Work will happen from 9:30 p.m. until 4:30 a.m. each night. Some work will occur during the daytime, when it can be done safely.

  1. What is being removed? Sections of the concrete barrier and concrete deck surface over OR 99E along northbound and southbound I-205 in preparation for girder removal. A large section of the northbound girder was removed April 13 (pictured above). 
  2. Why is the demolition being done now and where does it fit in the project? In order to install new steel girders and fittings to handle the upcoming widening on the Abernethy Bridge, some sections of the existing bridge deck need to be removed.
  3. Why is demolition work happening at night? Night work is needed since some demolition will occur directly above OR 99E and other areas with active vehicle and pedestrian foot traffic during the day. These areas need to be closed for safety purposes when traffic volumes are low.

Follow the progress live on the project construction cameras.

We know the noise from construction work can be disruptive. Again, we appreciate your patience.

Residents in the vicinity of the construction area should anticipate elevated noise levels while this work is occurring. A 24/7 nighttime noise hotline is available at: 503-276-7809.


Waterline installation along OR 43 continues

WEST LINN  Rock excavation work continues under the Abernethy Bridge on the West Linn side adjacent to OR 43.

This time-consuming work focuses on excavating channels through solid basalt to accommodate waterline installation to the proper depth. Approximately 250 feet of waterline pipe has been installed so far below the I-205 southbound onramp onto and across OR 43 during this effort. 

The majority of the work will happen between 7 a.m. and 8 p.m. Monday through Friday. There is a chance overnight excavation work may be necessary.


Project Traffic Impacts

As work activity increases, there are multiple lane reductions, ramp closures and signed detours occurring throughout the project area. Current and complete details and detour maps can be found on the project website.

April 25 - May 2 Traffic Impacts

  • I-205
    • None.
  • OR 99E
    • April 25 - Overnight lane closures on OR 99E southbound from 8 p.m. to 6 a.m. A single lane will remain open.
    • April 28-May 2 - Overnight lane closures on OR 99E northbound from 10 p.m. to 5 a.m. A single lane will remain open.
    • April 28-May 2 - Overnight ramp closure from OR 99E to I-205 northbound from 10 p.m. to 5 a.m.
    • Pedestrian detours on OR 99E.
  • OR 43
    • April 25-26 - Overnight lane closures on OR 43 northbound from 8 p.m. to 6 a.m.
    • April 25-May 2 – Lane closures at I-205.
    • Pedestrian detours on OR 43.
  • Local roads
    • April 28-30 - Daytime flagging on Main Street from 7 a.m. to 5 p.m. Monday through Wednesday.

The latest information on traffic impacts will be available at TripCheck.com.

As with any construction project, closure dates and timing are subject to change.


Future Work

Coming this summer, May-June 2025 (tentative)

Pile driving at the base of a bridge support near OR 99E will occur sometime in mid-May during the day (likely 7 a.m.-8 p.m.) for approximately four weeks. More details will be provided once confirmed.


Sign up for updates

Don't keep this a secret – help us spread the word!

Share this email with your friends, family and neighbors so they can also get connected and sign up to receive email and text updates to learn about the work we're doing.


What is this project?

ODOT is upgrading the Abernethy Bridge, which spans the Willamette River between Oregon City and West Linn, to withstand a major earthquake and widening it to accommodate a future third travel lane. Additional improvements are being made to the bridge's adjacent on- and off-ramps to improve safety. This work is expected to be completed in 2026.  


Work Zone Safety

Questions or comments?

Ryan McCrary, ODOT Community Affairs

Ryan.MCCRARY@odot.oregon.gov
503-983-5506

For more information, visit www.i205corridor.org 

 


Translation/Interpretation Accommodations

For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call 503-731-4128, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.

 

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128.

 

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128.

 

如果您想瞭解這個項目翻譯成 繁體中文 的相關資訊,請致電 503-731-4128.

 

如果您想了解这个项目翻译成 简体中文 的相关信息,请致电 503-731-4128.

 

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: 503-731-4128.

 

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.

 


For 24/7 road conditions and traffic alerts visit tripcheck.com or call 5-1-1.

 

Visit the Portland Area Construction Information website for more information about projects in construction.


Contact Us

If you have questions or comments, please contact:
Phone: 503-731-8276 | Email: 205improvements@odot.oregon.gov
Nighttime Noise Hotline: 503-276-7809

www.i205corridor.org