Jordan Valley
All concrete work is complete. Remaining tasks include:
- Electrical work for the rapid flashing beacon at U.S. 95 and Oregon Avenue.
- Paving is expected to be completed by May 10.
- All tasks, except finish work, expected to be completed by May 17.
- Finish work includes installing signs and re-striping highway and pedestrian markings.
|
|
 |