UPDATE: Southwest Oregon Construction Report for two weeks: March 24-April 6, 2024

 

NOTE: We have added a new project to the weekly Construction Report.

 

U.S. 101 (Oregon Coast Highway), MP 304, Tree removal along power line right of way

In cooperation with Coos-Curry Electric, contractors for ODOT will remove trees and brush from a short section of power line right of way south of Port Orford from milepost 304.0 to 304.1. Work is scheduled to begin Monday, April 1, and may continue through the week. Drivers should watch for intermittent lane closures and expect delays less than 20 minutes. Flaggers will provide traffic control as needed.

For more information, contact ODOT Public Information Officer Dan Latham at 541-817-5200 or Dan.Latham@odot.oregon.gov.