Construction Alert |
|
|
Work in Halsey continues and is expected to complete later this year
We've been working in Halsey to repair the road and make improvements for pedestrian and bicyclists accessing the downtown district.
We've made a lot of progress and are on track to finish this year. However, work is weather dependent and schedules may change.
|
In the next six months, we plan to:
- Install curbs, sidewalks and complete the base paving on the asphalt section from F Street to American Drive.
- Install curbs, sidewalks, repair the road base and complete the base paving on the concrete section from F Street to the south city limits.
This work is estimated to start June 19 and will require lane restrictions. A detour around Halsey using I-5 will be in place due to the 10 foot max lane width for vehicles and trucks.
Use caution – we've reduced the speed limit in the work zone to 25 m.p.h.
What's completed:
- We've installed new stormwater systems, including pipes and basins.
New swales were put in at Central Linn Elementary School and Crowell Lane.
- We've made the road more level north of F Street and installed sidewalks.
- We've built five new retaining walls throughout town with a decorative treatment.
|
|
Translation/Interpretation Accommodations
For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call 503-986-2600, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.
Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-986-2600.
Looking for a great job with a competitive salary and good benefits? Want to help your community every day? Apply now at ODOTJobs.com. Nothing quite fit? Check back often!
Having trouble viewing this email? View it as a Web page.
|
|
|
|