Map showing the locations of three bridges we're working on in the next two weeks.
D River Bridge
This week we're replacing the protective surface material on the D River bridge. We'll start work on Tuesday and we estimate finishing on Thursday. We're working nights, expect construction noise and lane closures starting at 7 p.m. to 6 a.m.
We estimate completing the project by installing the permanent striping on August 11.
Siltcoos River Bridge
We're completing all major work, including replacing the protective surface and applying permanent striping next week, August 8 - 10, on the Siltcoos River Bridge.
Schooner Creek Bridge
We estimate applying permanent striping, completing on the bridge, by August 11.
Learn more about the work we're doing on these bridges by visiting the project webpage.
Where traffic is routed through or around a work zone, pedestrians, including those with disabilities, will also be provided routes through or around the work zone.
|