U.S. 26 Paving Project: Cornell Road to Sylvan Interchange - Nighttime Paving to Begin June 27

Having trouble viewing this email? View it as a Web page.

Nighttime Paving Work to Begin June 27

Extensive paving will last through August

In addition to continuing Americans with Disabilities Act (ADA) ramp upgrades, crews will begin paving the portion of U.S. 26 that spans from SW Scholls Ferry Road to OR 217 on June 27. Once this section of work is complete, crews will begin paving between OR 217 and NW Cornell Road. Paving work is weather-dependent and is subject to change.

Nighttime construction work and traffic impacts can take place on any night, but will mostly follow a Sunday through Thursday schedule, in addition to ongoing curb ramp work during the day. Bridge work will start in August, and the project team will begin striping the roadway in September.

Night work will be suspended over the 4th of July holiday weekend.

Traffic Impacts

In order to maintain a safe work zone for travelers and construction crews during construction, travel lanes and segments of U.S. 26 and on- and off-ramps will close
to traffic on various nights. Traffic control with signed detour routes will be provided. Expect traffic delays.

Traffic impacts during construction include:

  • Nighttime full closures of U.S. 26 at interchanges within the project corridor.
    Traffic will be detoured to adjacent on- and off-ramps.
  • Nighttime single and double lane closures on U.S. 26. Single lane closures will begin as early as 8:30 p.m. and double lanes as early as 10 p.m. All lanes will open by 5:30 a.m. weekdays (later on weekends).
  • Nighttime lane closures and full closures of on- and off-ramps in the project area. These can happen as early as 9 p.m., open by 5 a.m. (later on weekends).
  • Lane closures on local streets, sidewalk closures and temporary ADA-accessible pedestrian detours where on- and off-ramps meet local streets.

Project Area

U.S. 26 Paving Project Area Map

View a Larger Map Here

Noise Impacts During Construction

Expect periodic construction noise, mostly from heavy equipment and construction trucks (example: required vehicle reverse noises) and other equipment such as paving and grinding machines, jackhammers, concrete saws and compressors.

Those working or living near the work areas may hear construction noise. ODOT will use construction noise mitigation measures to reduce noise impacts to surrounding neighbors.

Use the 24/7 nighttime noise hotline to reach a live person to discuss any noise concerns: 503-412-2349.

Schedule

ADA curb ramp work is ongoing, and will continue throughout the length of the project. Paving begins late June, followed by bridge work in August and roadway striping in September. All work is scheduled to be complete by the end of 2021.


Project Overview

ODOT is working throughout the summer and fall to improve approximately six miles of U.S. 26 (Sunset Highway) by repaving in both directions from Cornell Road to the Sylvan interchange, including several on- and off-ramps.

We are also repairing bridges and bridge joints in the project. Curb ramps at each repaved on- and off-ramp will also be upgraded to meet Americans with Disabilities Act (ADA) standards.

Project Benefits

  • A new road surface will improve the overall quality of U.S. 26 and several on- and off-ramps, resulting in a smoother and safer highway for drivers.
  • Bridge joint work will help to preserve and extend the life of this heavily traveled highway corridor.
  • Upgraded ADA curb ramps at on-and off-ramps will make a safer, more accessible highway for all, including people who walk, use mobility devices and who are visually impaired.

Let's all look out for each other. Drive, walk and ride safely. The way to go. Oregonians Stand out.

Question or Comments?

Lili Boicourt, ODOT Community Affairs
503-731-8247 | lili.d.boicourt@odot.state.or.us

To sign up for email alert, find current information and weekly updates:
bit.ly/us26pavingcornelltosylvan.


For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call 503-731-4128, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.

¿Habla usted español? Podemos proveer la información en esta publicación en español. Para recibir la información en español, por favor llamé al (503) 731-4128.

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128.

如果您想瞭解這個項目翻譯成 繁體中文 的相關資訊,請致電 503-731-4128. 如果您想了解这个项目翻译成 简体中文 的相关信息,请致电 503-731-4128.

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: 503-731-4128.

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.


Learn how we’re evolving to build a modern transportation system based on sufficient funding and equity: www.oregon.gov/odot/Pages/SAP


trip check

For 24/7 road conditions and traffic alerts visit tripcheck.com or call 5-1-1.

Visit the Portland Area Construction Information website for more information about projects in construction.