Delta Highway paving rescheduled for September
Delta Highway paving
Delta Highway will be paved between I-105 and Goodpasture Island Road this year, but the schedule has changed, and it will now occur in September. The project was originally scheduled to start August 16.
The eastbound I-105 ramp to northbound Delta Highway will close for one night, otherwise expect single lane closures for one week. Construction hours will be 8 p.m. to 5:30 a.m.
The section from Goodpasture Island Road to the interchange will be paved next year.
Beltline Highway paving
Beltline Highway is scheduled to be paved in September from just south of Roosevelt Blvd to West 11th Ave at night, 8 p.m. to 5:30 a.m. Expect single lane traffic and delays up to 20 minutes.
The OR 99 and Northwest Expressway interchange ramps will also be paved in September.
|