|
ODOT Region 2 | August 30, 2019 | 8_153_ R2_A4
Linn, Benton, Lincoln and Polk Counties state highway construction update
The Oregon Department of Transportation is committed to providing a safe and efficient transportation system. ODOT invests in Oregon’s future through roadway improvement projects. The following are located in ODOT Region 2, Area/District 4, including projects in Linn, Benton, Lincoln, and Polk Counties. All work is dependent on weather conditions.
Access for pedestrians, including those with disabilities, will be available and identified through or around the work zones. For updates on traffic, Know Before You Go at TripCheck.com or call 511.
U.S. 20 / OR 34: Philomath Blvd Apartments highway improvements A left turn lane, a right turn lane and a pedestrian crossing are being constructed as part of the new apartment complex development between Corvallis and Philomath.
Work not impacting travel lanes can be expected during the day. Lane closures may occur between 7 p.m. and 6 a.m. Watch for flaggers controlling traffic. Shawn Denney (541)757-4159, Carla Wahl (541) 757-4182
OR 223 Kings Valley Highway paving Crews have completed chip seal paving between mileposts 21.5 and 31.4. Striping is scheduled to be completed in the next several weeks. Shawn Martin (541) 967-2111
OR 99W Crack Sealing Crews are crack sealing OR 99W in various locations Tuesday through Thursday 9 a.m. to 4 p.m. and on Friday from 9 a.m. to 3 p.m. Guy Mamac (541) 757-4112
Lincoln County
OR 34: McKinney Slough Bridge replacement Bridge is substantially complete and roadway has been paved. Road is now open to traffic in both directions. Remaining work is scheduled to be completed in late September or early October. No delays expected at this time.
An existing bridge near milepost 1.5 has been replaced with a new structure. Steven Schultz (541) 757-4158
U.S. 101: Devil’s Lake Outlet, Schooner Cr & Siltcoos River Bridges At D River Outlet night work is complete for the season and work continues during the day underneath the bridge. Short duration lane closures are allowed from 7 p.m. to 9:30 p.m. but will only be needed on occasion. Work is expected to last until the spring of 2020.
Work at Schooner Creek Bridge begins with the installation of temporary signs and a temporary pedestrian crossing on the south side of the bridge. Night time lane closures are expected to begin the week of September 9 and continue for several months. Lane closures are allowed from Sunday night to Friday morning between 8 p.m. and 6 a.m. Expect minor delays.
This project includes the following improvements at each of the three bridges:
- Repair damaged concrete
- Install zinc anodes to the structures to protect them from the harsh coastal climate
- Replace bridge railings to meet current crash standards
- Install steel and titanium rebar to strengthen bridges
Steven Schultz (541) 757-4158
U.S. 101: Yaquina Bay Bridge painting The eastern sidewalk is closed for the duration of the project. A temporary pedestrian crossing at the south end of the bridge will allow pedestrians to cross U.S. 101. At the north end, pedestrians can use the existing sidewalks under the bridge, which will be signed as the pedestrian detour route. This project is expected to last until October 2019. Expect minor delays.
Most of the work is under the bridge with no impact to traffic. There will be occasional nighttime lane closures to set up containment under the bridge and move equipment. Intermittent night work will continue with lane closures allowed from 8 p.m. to 6 a.m.
This project is painting the steel bridge members under the roadway deck in two spans of the steel structure. These members are in need of additional protection from the harsh coastal environment. Steven Schultz (541) 757-4158
U.S. 101 Road Repairs Crews will be working between Lincoln City and Neskowin, mileposts 101, and mileposts 112 – 117, Tuesday through Thursday nights, 8 p.m. to 6 a.m. Guy Mamac (541) 757-4112
|