|
ODOT Region 2 | April 13, 2019 | 4_63_R2
Linn, Benton, Lincoln and Polk Counties state highway construction update
The Oregon Department of Transportation is committed to providing a safe and efficient transportation system. ODOT invests in Oregon’s future through roadway improvement projects. The following are located in ODOT Region 2, Area/District 4, including projects in Linn, Benton, Lincoln, and Polk Counties. All work is dependent on weather conditions.
Access for pedestrians, including those with disabilities, will be available and identified through or around the work zones. For updates on traffic, Know Before You Go at TripCheck.com or call 511.
Benton County
OR 34: Corvallis-Lebanon Highway: Flood cleanup and recovery
Monday, April 15, crews will begin removing debris, clearing culverts and rebuilding shoulders between Colorado Lake Drive and Peoria Road.
Single lane closures should be expected for at least two weeks. Heavy equipment will be regularly moving through the area.
The westbound right lane will be closed first, then crews will move to the eastbound right lane. Work in that section is expected to last at least a week.
Expect work between the bypass and Peoria Road the week of April 22. The multi-use path is anticipated to need repair as well. Brian Morey (541) 757-4211
Linn County
OR 34: Seven Mile Lane to Sunset Drive Paving
OR 34 will be repaved and shoulder rumble strips added between Seven Mile Lane and Sunset Drive, east of Interstate 5 and west of Lebanon.
Lanes will be closed for paving and 24-hour work zone speed restrictions. Watch for flaggers controlling traffic. Work on the western half of the project (mp 10.94-15.45) will be done during the day. Work on the eastern half (mp 15.45 - 16.83) will be done at night. No work will be done Friday - Sunday.
Work is scheduled to begin after May 1 and be completed by June 30. Jeff Shambaugh (503)986-5764
Lincoln County
OR 34: McKinney Slough Bridge Replacement
An existing bridge near milepost 1.5 is being replaced with a new structure. This new structure will be constructed one half at a time. Due to limited working space one lane of traffic will be closed for the duration of the project.
The South half of the new structure is now complete and crews have begun work on constructing the North half of the structure. One lane, two way traffic has been routed onto the completed half bridge. Traffic is controlled by a temporary signal or flaggers at all times. Expect minor delays. Steven Schultz (541)757-4158
U.S. 101: Devil’s Lake Outlet, Schooner Cr & Siltcoos River Bridges
This project includes the following improvements at each of the three bridges:
- Repair damaged concrete
- Install zinc anodes to the structures to protect them from the harsh coastal climate
- Replace bridge railings to meet current crash standards
- Install steel and titanium rebar to strengthen bridges
Night work continues until Memorial Day, but will be intermittent depending on weather. Lane closures are in effect from 7 p.m. to 6 a.m. Monday night through Thursday night. Flaggers are directing traffic at the signal at SE 1st St during lane closures. Crews are installing steel and titanium reinforcement to the bridge deck. Work at the Devil’s Lake Outlet bridge is expected to last until the spring of 2020. Work at Schooner Creek bridge is expected to start in summer of 2019. Expect minor delays. Steven Schultz (541)757-4158
U.S. 101: Yaquina Bay Bridge Painting
This project will paint the steel bridge members under the roadway deck in two spans of the steel structure. These members are in need of additional protection from the harsh coastal environment.
Most of the work will be done under the bridge with no impact to traffic. There will be occasional nighttime lane closures to set up containment under the bridge and move equipment. Intermittent night work will continue with lane closures allowed from 8 p.m. to 6 a.m. The eastern sidewalk is closed for the duration of the project. A temporary pedestrian crossing at the south end of the bridge will allow pedestrians to cross U.S. 101. At the north end, pedestrians can use the existing sidewalks under the bridge, which will be signed as the pedestrian detour route. This project is expected to last until October 2019. Expect minor delays. Steven Schultz (541)757-4158
|