Linn, Benton, Lincoln and Polk Counties state highway construction update: July 23 - 27

The Oregon Department of Transportation is committed to providing a safe and efficient transportation system. ODOT invests in Oregon’s future through roadway improvement projects. The following are located in ODOT Region 2, Area/District 4, including projects in Linn, Benton, Lincoln, and Polk Counties. All work is dependent on weather conditions.

 

Access for pedestrians, including those with disabilities, will be available and identified through or around the work zones. For updates on traffic, Know Before You Go at TripCheck.com, or call 511.

 

Linn County

Interstate 5 / OR 164: Love’s Travel Stop & Country Store Highway Improvements

Highway work is being done in preparation for a new travel stop. The I-5 northbound ramp / OR 164 intersection is now an all-way stop intersection. Construction is nearly completed. Lynn Detering (541)757-4211

 

Benton County

US 20 / Philomath Blvd: Boulevard Apartments (Philomath) - Water/Sewer Line Work

Water and sewer line work along and across the highway for a proposed apartment complex. The project will include highway improvements of a new left turn lane and pedestrian crossing. Expect lane closures Sunday night through Thursday night from 7 p.m. to 6 a.m.

Carla Wahl (541) 757-4211

 

OR 34: Harrison Blvd Bridge Repair (Corvallis)

Crews are repairing the abutment on the west side of the river. The pedestrian path adjacent to the abutment will be closed with a detour in place. There will be no impact to traffic on OR 34. The repair work is expected to last three to four weeks.

Brady Pauls (541) 757-4178

 

Benton/Polk County

OR 99W Monmouth – Lewisburg Paving

Crews will paving the roadway between Monmouth and Lewisburg beginning Sunday, July 15. Work will begin with the paving of approaches and turn outs, road repairs, and bridge work. Paving will be done north to south. After paving, rumble strips and striping will be completed. Work will be done at night, Sunday through Thursday, 7 p.m. to 6 a.m.

Steven Schultz (541)757-4158

 

Lincoln County

US101: Beverly Beach Drainage Improvement Project

A stormwater drainage system is being constructed. Beginning July 29, approximately one week of night shifts from 7 p.m. to 6 a.m., Sunday night through Friday morning. One lane will be closed on U.S. 101, expect minor delays of less than 20 minutes. Pipe work is scheduled to begin in August.

Steven Schultz (541)757-4158

 