ODOT Region 1 Weekly Construction Update: March 31-April 7
Oregon Department of Transportation sent this bulletin at 03/30/2018 12:35 PM PDT
March 30, 2018
For more information: Katelyn Jackson 503-731-8503
Katelyn.Jackson@odot.state.or.us
Weekly Construction Update:
March 31-April 7, 2018*
*Schedules are subject to change due to weather and site conditions.
1. Visit TripCheck. Constantly updated with construction and crash data, TripCheck is the best way to learn about roadway conditions around the state.
2. Scroll down to the highways listed below to see impacts that affect you. Construction information is shown for one week, giving you the most up-to-date information for targeted areas in the Portland-metro region
3. Review this "quick glance" schedule. Construction information is shown for one week in a visual format, giving you the most up-to-date information for targeted areas in the Portland-metro region.
Interstate 5 – Pacific Highway – Exit 283 on-ramp (City of Wilsonville)
Project Description: The City of Wilsonville is making improvements to the I-5 on-ramp for Exit 283 from Wilsonville Road.
Traffic Impacts: Day lane closures on the southbound Exit 283 on-ramp from Wilsonville Road from 8 a.m. to 2 p.m. and shoulder closures.
Interstate 5 – Pacific Highway – Paving and Auxiliary Lane
Project Description: This project will add a southbound auxiliary lane on I-5 from Lower Boones Ferry Road to I-205, add a second lane to the Lower Boones Ferry Road off-ramp from I-5 north, and pave I-5 from OR 99W to I-205.
Traffic Impacts: Nighttime single lane closure of I-5 in both directions from 8 p.m. to 5:30 a.m. Sunday through Thursday. Periodic shoulder closures.
For more information: www.tinyurl.com/I5ODOTProject
Interstate 5 – Pacific Highway – Interstate Sign Replacement
Project Description: This project will install, replace, repair and upgrade existing interstate signs and sign structures to meet current federal standards. The project area along I-5 will occur south of the Iowa Street viaduct and north of the OR 217 interchange.
Traffic Impacts: Expect nighttime on-and off-ramp closures from 10 p.m. to 5 a.m. and lane closures on I-5 from 8 p.m. to 5:30 a.m. weekdays. Use signed detours.
Tuesday night, the northbound Exit 297 off-ramp to Terwilliger Boulevard will be closed.
For more information: www.tinyurl.com/i5SignReplacementODOT2
Interstate 84 – Banfield Expressway – Regional Connections
Project Description: This project is the next phase of ODOT RealTime, a system that provides real-time traffic information on roads to help travelers get where they're going more safely and efficiently. New electronic signs will be installed on U.S. 26 between I-405 and OR 217. During sign installations, there will be several full nighttime freeway closures. Work will be complete spring 2018.
Traffic Impacts: Double lane closures on I-84 (from I-5 to I-205) for eastbound direction Monday through Friday, from 8 p.m. to 5:30 a.m.
For more information: www.odotrealtime.org
Interstate 84 – Columbia River Highway – Multnomah Falls sign installation
Project Description: This project will install a new electronic sign at the Multnomah Falls parking lot.
Traffic Impacts: No traffic impacts.
For more information: www.oregon.gov/odot/projects/pages/project-details.aspx?project=19642
Interstate 84 – Columbia River Highway – Farley Slide
Project Description: The project will repair a landslide area to prevent future movement near milepost 48, just east of Cascade Locks. The work will include building a retaining wall north side of I-84 below the highway.
Traffic Impacts: No traffic impacts.
For more information: www.i84construction.org
Interstate 84 – Columbia River Highway – Wyeth to Lindsey Creek
Project Description: This project is constructing the next phase of the Historic Columbia River Highway State Trail. This segment will connect Wyeth Campgrounds to the State Trail at Lindsey Creek. Construction will occur through summer 2019.
Traffic Impacts: Expect an around-the-clock single lane closure for eastbound I-84 from milepost 51-53 until mid-May. Periodic shoulder closures.
For more information: www.oregon.gov/ODOT/Regions/Pages/State-Trail.aspx
Interstate 205 – East Portland Freeway – Glenn Jackson Bridge to Johnson Creek Boulevard
Project Description: This project will pave 9 miles of I-205 between Johnson Creek Boulevard and the Glenn Jackson Bridge, including some ramps, build auxiliary lanes in three locations, install ODOT RealTime electronic signs and make pedestrian improvements at Glisan Street.
Traffic Impacts: Day shoulder closures from 7 a.m. to 5 p.m.
For more information: www.i205construction.org
U.S. 26 – Sunset Highway – Cornelius Pass Road to 185th Avenue
Project Description: This project will widen U.S. 26 to three lanes in each direction between Cornelius Pass Road and NW 185th Avenue, replace the two Rock Creek bridges with one bridge, improve the north side of the Cornelius Pass Road interchange and build a sound wall on the north side of U.S. 26 in the Rock Creek neighborhood.
Traffic Impacts: Day shoulder closures on U.S. 26.
For more information: www.cornpass185.org
U.S. 26 – Sunset Highway – Regional Connections
Project Description: This project is the next phase of ODOT RealTime, a system that provides real-time traffic information on roads to help travelers get where they're going more safely and efficiently. New electronic signs will be installed on U.S. 26 between I-405 and OR 217 and on I-84 between I-5 and I-205. New technology will be installed on TV Highway from OR 217 to Brookwood Parkway and on local Washington County roads. During sign installations on U.S. 26 and I-84, there will be several full nighttime freeway closures. Work will be complete in spring 2018.
Traffic Impacts: Night and day shoulder closures on U.S. 26. Single lane closure for eastbound U.S. 26 from 8 p.m. to 5:30 a.m. weekdays.
For more information: www.odotrealtime.org or 24-hour noise hotline at 971-673-5239.
U.S. 26 – Powell Boulevard – Safety Improvements
Project Description: This project will make safety improvements on Powell Boulevard from Southeast 20th to 35th Avenues. Improvements include installing pedestrian activated beacons, new signs improved lighting, and crosswalk and sidewalk improvements.
Traffic Impacts: Day and night single lane closures from 9 a.m. to 3 p.m. and from 8 p.m. to 6 a.m. weekdays.
Flagging at intersections. Flaggers will direct traffic at intersections of SE 21st, 26th and 33rd Avenues during night work.
For more information: www.powellblvdsafety.org
Oregon 8 – Tualatin Valley Highway – Regional Connections
Project Description: This project is the next phase of ODOT RealTime, a system that provides real-time traffic information on roads to help travelers get where they're going more safely and efficiently.
Traffic Impacts: Single lane closures and shoulder closures on 185th Avenue, Cornelius Pass, Murray Road and Scholls Ferry Road from 9 a.m. to 3 p.m. weekdays.
For more information: www.odotrealtime.org
Oregon 99W – Interstate Avenue – Victory Boulevard Bridge Repair
Project Description: Crews will replace rotting wooden bridge supports with steel supports on a bridge carrying Interstate Avenue for this emergency maintenance project. The bridge is located where North Interstate Avenue crosses over North Victory Boulevard, just west of Interstate 5 in North Portland
Traffic Impacts: Single lane closures in both directions 24/7 all days on Victory Boulevard.
Oregon 99W – Pacific Highway West – SW Naito to Capitol Highway (south end)
Project Description: This last part of this project will install new directional and street signs and poles on Barbur Boulevard between Terwilliger and the south end of Capitol Highway.
Traffic Impacts: Periodic nighttime single lane closures in both directions.
For more information: www.BarburSafety.org
Oregon 213– 82nd Avenue – SE Lindy Street to SE King Road
Project Description: This project will pave SE 82nd Avenue from SE Lindy Street to SE King Road and install new sidewalk curb ramps.
Traffic Impacts: Daytime lane closures from 6 a.m. to 3 p.m. weekdays on SE 82nd Avenue. Pedestrian and cyclist detours.
For more information: lmsc.82ndaveprojects.com
Oregon 213– Cascade Highway South – South Union Mills
Project Description: This project will improve safety on OR 213 at the intersection of South Union Mills Road by leveling out the crest of the hill to increase driver’s ability to see oncoming and turning traffic. This project will also add a standard right-turn lane on Union Mills and a center turning lane on OR 213 for southbound traffic.
Traffic Impacts: Daytime lane closures with flaggers directing traffic from 7 a.m. to 5 p.m. weekdays on South Union Mills Road.
For more information: www.OR213UnionMills.org
Oregon 213– Cascade Highway South – Highway repairs in Mulino
Project Description: Repair work is underway to install drains to create a path for water under the highway. Record setting rains reactivated an ancient landslide in March 2017. Roadway conditions will continue to change as additional movement of the landslide is expected.
Traffic Impacts: Travelers should expect flaggers directing traffic from 9 a.m. to 3 p.m. Tuesday through Friday. One lane in each direction is open other times. Speed is reduced to 45 mph.
For more information: www.oregon.gov/odot/projects/pages/project-details.aspx?project=SHHR
Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону (503) 731-4128.
이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: (503) 731-4128.
如果 您想了解这个项目翻译成简体中文的相关信息,请致电 (503) 731-4128.
For ADA (Americans with Disabilities Act) or Civil Rights Title VI accommodations, translation/interpretation services, or more information call (503) 731-4128, TTY (800) 735-2900 or Oregon Relay Service 7-1-1.