Area 1 construction update
Oregon Department of Transportation sent this bulletin at 02/23/2018 07:56 AM PSTHaving trouble viewing this email? View it as a Web page.
ODOT Region 2 February 23, 2018 | 2-30-R2 | For Immediate Release
Shane Ottosen, Project Manager, (503) 325-4732 ext. 12
Lisa Nell, Area Manager, (503) 986-2764
Clatsop, Tillamook, Washington and Columbia Counties state highway construction update: February 27 – March 5
US30 (Astoria) Signal Upgrades Project (Clatsop County)
(Various locations – Commercial St and Marine drive between 9th and 14th Streets, Duane at 11th St. )
This project consists of performing constructing traffic signal modifications.
Flaggers will control single lane traffic along with single lane closures during construction when work is occurring as required. Minor delays should be expected when single lane closures are occurring and the public is reminded to drive through the area with caution. Pedestrian access will be maintained.
US30: Clatskanie Bluffs Rockfall Sec. Rockfall Repair and Screening
(Lower Columbia River Highway, MP 63.03 to MP 63.12)
This project consists of performing work as follows:
- Scale Slopes and remove debris
- Clear trees from top of slopes
- Install wire mesh slope protection
- Repair road surface
- Install permanent pavement markingsFlaggers will control single lane traffic during construction when work is occurring as required. Minor delays should be expected when single lane closures are occurring and the public is reminded to drive through the area with caution. One or more lanes may be closed when allowed shown or directed during the following periods and times:Monday through Friday from 9:00 A.M. to 4:00 P.M.Excepting those times as indicated in 00220.40(e-2)The project is scheduled to be completed in not later than July 31st, 2018. (Nehalem Highway, MP 69.72 to MP 69.87)
This project consists of performing work as follows:
OR47 Beaver Creek Bridge replacement Project (Washington County)
- Construct Work Area isolation and remove existing bridge.
- Construct pile foundations, abutments and bridge superstructure.
- Install drainage and storm water facilities and roadway paving.
- Install cast in place retaining wall.
- Perform additional and incidental Work as called for by the Specifications and plans
US101 Slide MP 81.1 Beaver Emergency Project (Tillamook County)This project consists of installing soil nails and slope protection on the east side of the highway as an emergency repair.Flaggers will control single lane traffic along with single lane closures during day hours between 7:30 and 5:00 pm when work is occurring as required. Minor delays should be expected when single lane closures are occurring and the public is reminded to drive through the area with caution.
This work is expected to be completed at the end of March.
Flaggers will control single lane traffic along with single lane closures during tree removal from February 19th through February 28th, 2018. Minor delays should be expected when single lane closures are occurring and the public is reminded to drive through the area with caution. Full road closure is not anticipated until June, 2018.
- .
U.S. 101/OR6 Traffic Improvement Project in Tillamook
This project improves traffic operations and performance, and increases safety on U.S. 101 and OR 6 through downtown Tillamook and across Hoquarton Slough.
The project will lengthen the U.S. 101 couplet to the Hoquarton Slough by extending Pacific Avenue north beyond 1st Street and replacing the existing slough bridge with a new four-lane bridge. The new bridge will be up to 5 feet higher than the existing bridge. The project will also widen the travel lanes on Main and Pacific Avenues from 1st to 4th Streets. Turn lanes will be added at key intersections through town. The project also improves the Hoquarton Interpretive Area, and adds gateway elements and downtown beautification.
Travelers can expect daytime and night time work and occasional lane closures.
Look for construction vehicles entering and leaving the highway.
The project is expected to be completed in the fall of 2018.
# # ODOT # #