Central Oregon Road Construction UPDATE: Week of April 24, 2017

 For further information contact:

Peter Murphy

541-388-6224

The Oregon Department of Transportation (ODOT) is continuing to invest in Oregon’s future with roadway improvement projects throughout Oregon’s central region (ODOT Region 4). ODOT is committed to providing a safe, efficient transportation system. The following projects reflect ODOT’s commitment to make improvements as traffic numbers rise and to make the roadways safer and more efficient for drivers. All work is dependent on weather conditions. Red denotes new or updated information.

DESCHUTES COUNTY

US97 @ Wickiup Jct. (La Pine)

For the week of April 24th, 2017. The contractor will be installing rebar for the bridge as well as other miscellaneous bridge work will be occurring all week. All work will be occurring off of the current highway alignment, therefore, no delays are expected.

US20 @ Barclay (Sister) Project

For the week of April 24th, 2017. EB and WB US20 traffic will be separated with the contractor working in the middle. They will be performing concrete paving during the week, with some night work involved. McKinney Butte will also be closed starting Monday, April 24th as the contractor begins excavation and utility work on that side of the roadway. The contractor will be starting to work both Saturdays and Sundays. If night work does occur motorists can expect delays of around 5-10 minutes. No delays, other than the detour for left turns in and out of Barclay and the closure of McKinney are anticipated during daytime hours next week.

 

JEFFERSON COUNTY

 

US26: Gumwood Lane - Earl Street Sec.

For the week of April 24th, 2017. The contractor will be working nights Sunday through Friday Morning at 8 pm to 8 AM. The construction will consist of grinding and paving on US26. Delay's could be up to 20 minutes.

Starting Monday night at 8 pm the contractor will beginning grinding and paving operations on US26. Delay could be up to 20 minutes at night and no delay during daytime after 8 am. Gumwood will remain closed throughout the week.

 

WASCO COUNTY

I84: Mosier - The Dalles Sec.

For the week of April 24, the Contractor will be performing single lane closures on I-84 EB & WB between MP 84 - MP 76 from 7pm to 7am.

Also, the Contractor will be working on the ramp shoulders from 7pm-10pm and closing the ramps from 10pm to 5am.

  • Exit 76 EB on and off will be closed April 23rd & 24th from 10pm - 5am
  • Exit 82 EB on and off will be closed April 25th from 10pm - 5am
  • Exit 83 EB on and off will be closed April 26th & 27th from 10pm - 5am

Please plan your trip accordingly. Speeds have been reduced to 50mph through the construction zone.

####